48 V. ASSESSMENT OF THE AID › Production of a ship at the Ancona shipyard and effects on the Palermo shipyard, Decision_act (EU) 2006/639

In forcesince 23 Nov 2005

Furthermore, Italy informed the Commission that already in June 2001 (less than six months after the contract for the five cruise ships was signed) there was a production crisis at Palermo, even without the extra work planned, which made it necessary to delay deliveries. The Commission therefore considers that the Palermo yard would not have been able to fulfil the December 2000 plan as regards outfitting, and Italy has not given any reply on this point.