40 V. ASSESSMENT OF THE AID › Legal basis, Decision_act (EU) 2006/639

In forcesince 23 Nov 2005

Article 3(2) stipulates, however, that the Commission may grant an extension of the three-year delivery limit when this is found justified by the technical complexity of the individual shipbuilding project concerned or by delays resulting from unexpected disruptions of a substantial and defensible nature in the working programme of a yard due to exceptional circumstances, unforeseeable and external to the company. It should be noted that Italy bases its request for extension of the delivery limit on such exceptional and unforeseeable circumstances.