19 III. COMMENTS FROM INTERESTED PARTIES, Decision_act (EU) 2006/639

In forcesince 23 Nov 2005

It also stated that the Ancona shipyard would have had no problems building an entire cruise ship of the dimensions and design characteristics of ship 6077 (the sister ship of 6079), including all fittings, using only its own production facilities, infrastructure and plant, if only the agreement between Fincantieri, the local and regional authorities, the port authorities and the metalworkers’ unions set out in the memorandum of intent of 6 December 1999 had been implemented immediately. However, this did not take place.