The amount paid by NILEG to GMH under the contract is even less than the expenses thus far incurred by GMH for having accepted to take part in this operation: the price of the furnace acquired was much higher in order to be able to recycle the dust and the running costs of this special furnace are much higher (particularly in electricity) than those of a normal production furnace. Also, if the company is to readapt the existing furnace to its normal production needs, it has again to incur high expenses.
The DEM 61,64 million paid by NILEG was used to cover that extra cost of the furnace (DEM 17 million) and the costs of recycling incurred until the end of 1996 (DEM 55 million). By then, GMH had informed NILEG that the recycling cost could not be brought down to much less than DEM 400/tonne, stopped the recycling operation and requested NILEG to revise the initial contract price upwards (the request was not accepted for lack of money). Also, during the first half of 1997, GMH claimed to have incurred DEM 2,5 million more as running costs, with its own production activity, because of the particularities of the electric arc furnace.
In a letter dated 26 June 1998, Germany also argued that GMH should be allowed to keep the amount corresponding to the extra expenses it had incurred as this did not constitute aid, and it arrived at an amount of DEM 38,586 million which it considered to be the aid paid to GMH. This amount would still have to be reduced by the negative selling price in view of the cancellation of the sale of the Westerkamp site.
As regards the third parties' comments, Germany reiterated its position that GMH had no legal obligation to recycle the dust and that therefore there was no aid involved. As to the particular comments made by the United Kingdom Permanent Representation to the European Union concerning the 'incentive for a potential buyer`, Germany pointed out that GMH was formed in April 1993 and that the amount in question was paid under a contract subsequently entered into with the new company. As to the comments made by Neue Maxhütte concerning the Relux contract, Germany stated that the data on which the comments were based were not accurate, since the Relux contract related only to the dust newly produced by GMH, the transport costs were not included in the contract price but were GMH's responsibility and the quantity of old dust was not 150 000 tonnes but 300 000 tonnes.