5. ASSESSMENT OF THE DEROGATION REQUEST CONCERNING MELILLA › 5.3. Scope of the derogation › 5.3.3. Chapter II of Regulation (EU) 2019/943: General rules for the electricity market – Articles 3 and 6, Articles 7(1), 8(1) and (4), Articles 9, 10 and 11 › 5.3.3.2. Assessment, Decision_act (EU) 2025/1016

In forcesince 16 May 2025
(69)

Concerning the request for derogation from Article 3, first paragraph, of Regulation (EU) 2019/943, the Commission considers that:

the reasons set out in recitals 9 to 12 currently entail that electricity prices in Melilla are not formed following a market-based approach but via a special regulated mechanism whereby the system operator carries out the generation dispatch for each of the NPT, and a derogation from Article 3, first paragraph, points (a), (b), (e), (k), of Regulation (EU) 2019/943 is justified.

the reasons set out in recitals 9 to 12 currently entail that there is no forward market in Melilla and the system operator’s dispatch involves weekly, daily, intraday forecasting as well as deviations in real time, and a derogation from Article 3, first paragraph, points (o) and (p), of Regulation (EU) 2019/943 is also justified.

while acknowledging that the current regulated system and particular characteristics of Melilla might render more difficult the development of more flexible generation, low carbon generation and more flexible demand, the application of the market rules is still required to incentivise their development to the extent possible. Thus, the Commission considers that a derogation from Article 3, first paragraph, point (c), of Regulation (EU) 2019/943 is not justified,

Article 3, first paragraph, point (j), of Regulation (EU) 2019/943 does not prevent that priority is given to energy storage projects in Melilla, if for example, those projects are considered as the best option to ensure security of supply. Thus, the Commission considers that a derogation from Article 3, first paragraph, point (j), of Regulation (EU) 2019/943 is not justified.

in relation to Article 3, first paragraph, point (n), of Regulation (EU) 2019/943, the entry or exit of an undertaking in the market for electricity generation should depend on that undertaking’s assessment of economic and financial viability, taking into account the possibility to receive the regulated remuneration mentioned in recitals (15) and (16). Hence, a derogation from Article 3, first paragraph, point (n), of Regulation (EU) 2019/943 is not justified for Melilla.