2. THE BALEARIC ISLANDS › The electricity system and electricity market in the Balearic Islands, Decision_act (EU) 2025/1014

In forcesince 16 May 2025
(14)

Spain further explains that electricity generated in all the NPT, including the Balearic Islands, is excluded from the bidding system on the mainland market. NPT electricity systems use a mechanism of economic precedence for dispatch [The framework is set out in Royal Decree 738/2015 of 31 July 2015 (Real Decreto 738/2015, de 31 de julio, por el que se regula la actividad de producción de energía eléctrica y el procedimiento de despacho en los sistemas eléctricos de los territorios no peninsulares) (‘Royal Decree 738/2015’).]:

the system operator ranks the generation plants in order of economic merit based on variable costs until demand is covered, taking into account the technical constraints and the reserves necessary to guarantee electricity supply;

the dispatch involves weekly, daily, intraday forecasting as well as deviations in real time. In the Balearic system, the dispatch also takes into account the maximum exchange of electricity available through the interconnection with the mainland;

the demand side (direct consumers and suppliers) notifies the system operator of the hourly demand in the electricity systems of each NPT;

following the daily dispatch, the demand side purchases the energy at a price equivalent to that of the bidding system on the mainland.