Based on the Ministerial Order TEC/212/2019 of 25 February 2019, the 2021-2026 electricity transmission network plan provides for a second cable linking the Balearic Islands’ electricity system with mainland Spain. The cable is expected to be operational by 2030 (best estimation provided by Spain, 2029) and to cover up to 65 % of the Balearic Islands’ electricity supply [See Spain’s final updated National Energy and Climate Plan 2021-2030, 211d83b7-b6d9-4bb8-b084-4a3bfb4cad3e_en.].