45 5. ASSESSMENT OF THE DEROGATION REQUEST CONCERNING THE BALEARIC ISLANDS › 5.2. Substantial problems for the operation of the system › 5.2.2. Substantial problems presented by Spain in the Application, Decision_act (EU) 2025/1014

In forcesince 16 May 2025

Spain underlines that, due to the higher costs of producing electricity and the lack of effective competition, the integration of the NPT, including the Balearic Islands in the mainland (and European) electricity market would result in market distortions, and that this will be the case as long as the interconnections with mainland Spain do not suffice to cover the totality of the local demand.