60 5. ASSESSMENT OF THE DEROGATION REQUEST CONCERNING THE BALEARIC ISLANDS › 5.3. Scope of the derogation › 5.3.3. Chapter III of Regulation (EU) 2019/943: Network access and congestion management – Articles 14 to 17 and Article 19 › 5.3.3.1. The Application, Decision_act (EU) 2025/1014

In forcesince 16 May 2025

Spain explains that the requirements set out in Articles 14 to 16 and Article 19 cannot be applied in the NPTs, because the TSO carries out the generation dispatch for each of the electricity systems in these territories and those systems do not constitute separate interconnected bidding zones. Those dispatches take into consideration the energy transferred via links between mainland Spain and the Balearic Islands. In the event of congestion in those links, the TSO reorganises the dispatch of the available generating capacity, taking into account mainly technical criteria, to ensure supply. Spain also explains that since the NPT do not constitute separate bidding zones, there is not an associated cross-zonal capacity market and thus no congestion income is generated.