The new cables increasing the connection between the Balearic Islands and the Spain’s mainland are expected to become operational by the end of 2030. Once these cables start to operate, the regulatory framework applicable to this territory should be amended, this territory should be incorporated to the mainland electricity market and the requested derogations should be phased out. Spain argues that once that the cables are commissioned, additional time will be needed in order to incorporate these territories to mainland market rules, and to make the necessary regulatory changes and testing. Following this, Spain requests the derogations for the Balearic Islands at least until 2030.
84 5. ASSESSMENT OF THE DEROGATION REQUEST CONCERNING THE BALEARIC ISLANDS › 5.5. Duration of the derogation and conditions aiming to increase competition and integration with the internal market for electricity, Decision_act (EU) 2025/1014
In forcesince 16 May 2025