It is intended for the Baltic States to be synchronised with the Continental Europe Synchronous Area by one double circuit line connecting Poland and Lithuania. Upon synchronisation, the capacity of that line will have to be, in large part, reserved for reliability margins in a case of unexpected outage in the Baltic System and resulting unintended deviations. Transmission system operators should continue offering maximum capacity for cross-border trading, compliant with operational security limits and considering possible contingencies in the Polish and Lithuanian systems, including those resulting from outages of high-voltage direct current lines or disconnection of the Baltic States from the Continental Europe Synchronous Area. The specific situation of that interconnection should be taken into consideration for the calculation of the total capacity and contingencies pursuant to Article 16(8) of Regulation (EU) 2019/943.
Recital 54, Regulation (EU) 2024/1747
In force