46 5. ASSESSMENT OF THE AID › 5.1. Competence of the Commission, Decision_act (EU) 2007/257

In forcesince 20 Dec 2006

On the other hand, aid implemented after accession would constitute new aid and would fall within the competence of the Commission under the procedure laid down in Article 88. For the purpose of determining the moment when a given aid measure was put into effect, the relevant criterion is the legally binding act by which the competent national authority undertook to grant aid [Judgment of the Court of First Instance of 14 January 2004 in Case T-109/01 Fleuren Compost v Commission [2004] ECR II-127, paragraph 74.].

  • Judgment of the Court of First Instance (Second Chamber, extended composition) of 14 January 2004. Fleuren Compost BV v Commission of the EuDecision

    14 Jan 2004 · 62001TJ0109

  • Treaty establishing the European Community88Law