Of these projects totalling 7,2 million tons of SGA, the parties would have only [15 % - 25 %] *. However, the expansion projects of the parties are all underway and will be completed on schedule. For most of the other listed projects the completion date is speculative and in those cases where the estimated completion date will fall into the year 2004 (Indal, Ewarton), clearly beyond what the Commission can take into account for merger analysis. Moreover, several of the large expansion projects are planned by integrated companies for their increased internal needs. Those companies, which include Alcan, share the incentive to increase the price of SGA with the parties, since such a move would increase the cost of their rivals, which are not integrated.
Recital 37, Decision_act (EU) 2002/174
In forcesince 3 May 2000