Recital 35, Decision_act (EU) 2002/174

In forcesince 3 May 2000

Brownfield expansions are expansions of existing sites by, normally, adding new capacity of between 100,000 and 1 million tonnes at a cost below USD 800 per ton. Lead-time is normally between 2 and 3 years. Experience shows that, with the exception of Alcoa, backward integration is the major driving force for refinery expansions. The Commission's enquiry has shown that most of the brownfield expansions currently underway are mainly intended to cover the internal needs of the major integrated producers. This will inhibit the growth of third parties' sales of alumina in the western world and will probably reduce the ratio of the merchant market for alumina compared with overall alumina production (as was stated in paragraph 13, the alumina sold in the merchant market is now one third of total production). Dependency on third-party suppliers will probably be reduced for the major western integrated smelters.