In order to delimit the scope of this communication, and before specifying which regime applies to concessions, their distinctive features must be described. To this end, a brief review of the concept of works concessions as found in the works Directive should prove useful.
2.1. WORKS CONCESSIONS
2.1.1. Definition as given in Directive 93/37/EEC
The Community legislator has chosen to base its definition of works concessions on that of public works contracts.
The text of the works Directive states that public works contracts are "contracts for pecuniary interest concluded in writing between a contractor and a contracting authority (...) which have as their object either the execution, or both the execution and design, of works related to one of the activities referred to in Annex II or a work (...), or the execution by whatever means of a work corresponding to the requirements specified by the contracting authority" (Article 1(a)).
Article 1(d) of the same Directive defines a public works concession as "a contract of the same type as that indicated in (a) except for the fact that the consideration for the works to be carried out consists either solely in the right to exploit the construction or in this right together with payment".
According to this definition, the main distinctive feature of a works concession is that a right to exploit a construction is granted as a consideration for having erected it; this right may also be accompanied by payment.
2.1.2. Distinction between the concepts of "public works contract" and "works concession"
The Commission believes that the right of exploitation is a criterion that reveals several characteristics which distinguish a works concession from a public works contract.
For example, the right of exploitation allows the concessionaire to demand payment from those who use the structure (e.g. by charging tolls or fees) for a certain period of time. The period for which the concession is granted is therefore an important part of the remuneration of the concessionnaire. The latter does not receive remuneration directly from the awarding authority, but acquires from it the right to obtain income from the use of the structures built(7).