CPDA 1981, s. 5b

Extension of time limit during challenge

In forcesince 31 Jan 2024cited 111×
(1)

If an application is made under section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order), the applicable period for the purposes of section 5A is to be extended by—

(a)

a period equivalent to the period beginning with the day the application is made and ending on the day it is withdrawn or finally determined, or

(b)

if shorter, one year.

(2)

An application is not finally determined for the purposes of subsection (1)(a) if an appeal in respect of the application—

(a)

could be brought (ignoring any possibility of an appeal out of time with permission), or

(b)

has been made and not withdrawn or finally determined.

The 10 that are cited most themselves, of 111.

  • Levelling-up and Regeneration Act 2023185Law

    … is— (a) 3 years, or (b) such longer period as is specified in the order for the purposes of this section. ; (b) in section 5B (extension of time limit during challenge), in subsection (1), for “three year period mentioned in” …

  • The Hornsea Three Offshore Wind Farm Order 202022Law

    … “, and this subsection” to the end. (5) Section 5A (time limit for general vesting declaration) is omitted. (6) In section 5B (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application …

  • The Cottam Solar Project Order 202424Law

    … “and this subsection” to the end. (5) Section 5A (time limit for general vesting declaration) is omitted. (6) In section 5B(1) (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 …

  • The Gate Burton Energy Park Order 202422Law

    … “and this subsection” to the end. (5) Section 5A (time limit for general vesting declaration) is omitted. (6) In section 5B(1) (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 …

  • The Levelling-up and Regeneration Act 2023 (Commencement No. 2 and Transitional Provisio…Law

    … It amends sections 4 and 4A of the Compulsory Purchase Act 1965 and sections 5A and 5B of the Compulsory Purchase (Vesting Declarations) Act 1981, which set out the current statutory time limits within which compulsory purchase powers …

  • The Norfolk Vanguard Offshore Wind Farm Order 202222Law

    … execution of declaration) is omitted. (5) Section 5A (time limit for general vesting declaration) is omitted. (6) In section 5B (extension of time limit during challenge)— (a) for “section 23 of the Acquisition of Land Act 1981 …

  • The Norfolk Boreas Offshore Wind Farm Order 202122Law

    … execution of declaration) is omitted. (5) Section 5A (time limit for general vesting declaration) is omitted. (6) In section 5B (extension of time limit during challenge)— (a) for “section 23 of the Acquisition of Land Act 1981 …

  • The Five Estuaries Offshore Wind Farm Order 202526Law

    … (earliest date for execution of declaration). (5) Omit section 5A (time limit for general vesting declaration). (6) In section 5B(1) (extension of time limit during challenge)— (a) for “section 23 of the Acquisition of Land Act 1981 …

  • The West Burton Solar Project Order 202524Law

    … 5(2) (earliest date for execution of declaration) omit the words from “and this subsection” to the end. (5) In section 5B(1) (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application …

  • The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 202421Law

    … “, and this subsection” to the end. (5) Section 5A (time limit for general vesting declaration) is omitted. (6) In section 5B (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application …