The Five Estuaries Offshore Wind Farm Order 2025
- 21Compulsory acquisition of land
- 22Time limit for exercise of authority to acquire land compulsorily
- 23Compulsory acquisition of rights
- 24Compulsory acquisition of land: minerals
- 25Private rights
- 26Application of the 1981 Act
- 27Acquisition of subsoil only
- 28Modification of Part 1 of the 1965 Act
- 29Rights under or over streets
- 30Temporary use of land for carrying out the authorised development
- 31Temporary use of land for maintaining the authorised development
- 32Statutory undertakers
- 33Recovery of costs of new connections
- 34Funding
- 35Application of landlord and tenant law
- 36Felling or lopping of trees and removal of hedgerows
- 37Trees subject to tree preservation orders
- 38Abatement of works abandoned or decayed
- 39Saving provisions for Trinity House
- 40Crown rights
- 41Protective provisions
- 42Application of the 1990 Act
- 43Certification of plans, etc.
- 44Service of notices
- 45No double recovery
- 46Requirements
- 47Arbitration
- 48Compensation
- 1Time limits
- 2Offshore design parameters
- 3Aviation safety
- 4Stages of authorised development onshore
- 5Onshore substation works, design and landscaping
- 6Code of construction practice
- 7Traffic and access plans
- 8Permanent highway accesses
- 9Onshore archaeology
- 10Landscape and Ecological Management Plan
- 11Soil Management Plan
- 12Protected species onshore
- 13Ground water monitoring
- 14Restoration of land used temporarily for construction
- 15Control of noise during operational stage
- 16Skills and employment strategy
- 17Onshore build options
- 18Compensatory Works
- 19Reuse of temporary works with the onshore works for North Falls
- 20Biodiversity net gain
- 21Offshore decommissioning
- 22Onshore decommissioning
- 23Migratory bat monitoring
- 24Landfall drilling risk assessment
- 25Farmland bird compensation
- 26Requirement for written approval
- 27Amendments to approved details
2 Approval of matters specified in requirements
1 Protection for electricity, gas, water and sewerage undertakers
2 For the protection for operators of electronic communications code networks
3 For the protection of the Environment Agency
- 15
- 16Submission and approval of plans
- 17Construction of protective works
- 18Timing of works and service of notices
- 19Works not in accordance with this Part of this Schedule
- 20Maintenance of works
- 21Remediating impaired drainage work
- 22Agency access
- 23Free passage of fish
- 24Monitoring of Sea Defence
- 25As built drawings
- 26Heavy vehicle movements during construction
- 27Indemnity
- 28Disputes
4 For the protection of drainage authorities
5 For the protection of Network Rail Infrastructure Limited
6 For the protection of National Highways
- 65Application etc.
- 66Interpretation
- 67General
- 68
- 69Works outside the Order limits
- 70Prior approvals
- 71Construction of the cable works and SRN works
- 72Payments
- 73Provisional Certificate for SRN works
- 74Provisional Certificate for cable works
- 75Opening
- 76Final condition survey
- 77Defects Period
- 78Final Certificate
- 79Security
- 80Commuted sums
- 81Insurance
- 82Indemnity
- 83Maintenance of the authorised development
- 84Land
- 85Expert Determination
7 For the protection of London Gateway Port
8 For the protection of North Falls Offshore Wind Farm
9 For the protection of Port of London Authority (onshore)
10 For the protection of the Port of London Authority (offshore)
11 For the protection of Essex County Council as local highway authority
- 125Application
- 126Definitions
- 127Design input and commencement
- 128
- 129Survey reinstatement
- 130Inspections and testing of materials
- 131Road Safety Audits
- 132Defects in local highways constructed by the undertaker
- 133Provisional Certificate
- 134Maintenance
- 135Final Certificate
- 136Emergency Work
- 137Land interests
- 138Disputes
12 For the protection of Anglian Water
13 For the protection of Affinity Water
- 156Application
- 157Interpretation
- 158On street apparatus
- 159Apparatus in stopped up streets
- 160Protective works to buildings
- 161Acquisition of land
- 162Removal of apparatus
- 163Facilities and rights for alternative apparatus
- 164Specified works
- 165Expenses and costs
- 166Indemnity
- 167Cooperation
- 168Expert Determination
- 169Access
14 For the protection of National Grid Electricity Transmission
15 For the protection of Cadent Gas Limited
- 183Application
- 184Interpretation
- 185On Street apparatus
- 186Access to Apparatus
- 187Protective works to buildings
- 188Acquisition of land
- 189Removal of apparatus
- 190Facilities and rights for alternative apparatus
- 191Retained apparatus: protection of Cadent
- 192Expenses
- 193Enactments and agreements
- 194Co-operation
- 195Access
- 196Arbitration
- 10Design parameters
- 11
- 12Maintenance of the authorised development
- 13Vessels under the undertaker’s control
- 14Extension of time periods
- 15Notifications and inspections
- 16Aids to navigation
- 17Colouring of structures
- 18Aviation safety
- 19Chemicals, drilling and debris
- 20Force majeure
- 21Pre-construction plans and documentation
- 22
- 23Site Integrity Plan
- 24Offshore safety management
- 25Reporting of engaged agents, contractors and vessels
- 26Pre-construction monitoring and surveys
- 27Construction monitoring
- 28Monitoring of underwater noise from piling
- 29Post-construction monitoring
- 30Timing of monitoring report
- 31Reporting of impact pile driving
- 32Maintenance reporting
- 33Stages of construction
- 34Completion of construction
- 35
- 36Reporting of scour and cable protection;
- 37Deployment of cable protection
- 10Design parameters
- 11
- 12
- 13Maintenance of the authorised development
- 14Vessels under the undertaker’s control
- 15Extension of time periods
- 16Notifications and inspections
- 17Aids to navigation
- 18Colouring of structures
- 19Aviation safety
- 20Chemicals, drilling and debris
- 21Force majeure
- 22Pre-construction plans and documentation
- 23
- 24Site Integrity Plan
- 25Offshore safety management
- 26Reporting of engaged agents, contractors and vessels
- 27Pre-construction monitoring and surveys
- 28Construction monitoring
- 29Monitoring of underwater noise from piling
- 30Post-construction monitoring
- 31Timing of monitoring report
- 32Reporting of impact pile driving
- 33Maintenance reporting
- 34Stages of construction
- 35Completion of construction
- 36
- 37Reporting cable protection
- 38Deployment of cable protection
Source: legislation.gov.uk (The National Archives), UK legislation with its point-in-time versions. Official publication. Reuse: Open Government Licence v3.0.