Based on the information provided by the Spanish authorities, the Commission has checked the definition of ‘production unit’ as used in the restructuring plan. In the past, Spain carried out the analysis of the aid at undertaking level, und underground coal workings were calculated together with opencast workings. Spain has now changed this analysis and it checked the aid per production unit as defined in Regulation (EC) No 1407/2002. Furthermore, in this respect, Spain has provided the Commission in this respect with the information required by Decision 2002/871/EC. Therefore, the Commission considers that the definition of ‘production unit’ which Spain has used in its restructuring plan is in accordance with the Regulation.
87 4. ASSESSMENT OF THE AID › 4.4. Aid for reduction of activity (Article 4) of Regulation (EC) No 1407/2002) and aid for accessing coal reserves (Article 5(3) of the Regulation) › 4.4.2. Criteria to be applied, Decision_act (EU) 2011/693
In forcesince 21 Dec 2005
- celex=32002R1407