In its letter of 30 March 2004, the Commission considered that the proposal to reserve 30 % of the coal consumption (equivalent to approximately 100 days of consumption) for the power plants in the region, might be considered as incompatible with the common market with regard to Hunosa.
108 4. ASSESSMENT OF THE AID › 4.6. Hunosa plan, Decision_act (EU) 2011/693
In forcesince 21 Dec 2005