In the event of bankruptcy and of the non-implementation of asset deal 2, the BvS would have been faced with final costs of DEM 2590000. The BvS would have had receipts of DEM 2270000 (DEM 1800000 of the purchase price under asset deal 1 plus an estimated DEM 470000 from the sale of the site where the fourth production line was located). It would have incurred costs of DEM 4860000 in connection with the closure of the fourth production line, the reclamation of the site of the fourth production line and administration pending sale of the site.
Recital 74, Decision_act (EU) 2002/185
In forcesince 12 Jun 2001