In force

On 26 June 1968 the producers agreed not to build any new zinc production capacity without first informing the ZPG. They undertook to submit their production figures (tonnes of zinc produced) to the full ZPG meeting for approval. At the same time they agreed to make an across-the-board 20 % cut in their production (Appendix 1 to the minutes of the ZPG meeting).

Further output limitation agreements were made by all the firms concerned in 1967, 1969 to 1972 (1970: across-the-board reduction of 15 % - Penarroya note of 30 October 1970) and 1974 to 1976. For October 1975, for example, the ZPG announced production quotas to be observed by all the firms concerned. The reference production tonnage allotted to Penarroya/Pertusola was around 20 000 tonnes and that allotted to RTZ (AMSE) around 42 000 tonnes (AMSE memorandum dated 13 August 1975).