37 COMMISSION ASSESSMENT › Assessment of the revised performance targets › Assessment of the capacity-related measures invoked by Luxembourg to justify the observed deviations from the Union-wide cost-efficiency trends › Assessment of modified Measure 1, Decision_act (EU) 2024/343

In forcesince 13 Dec 2023

The Commission notes that increased cost estimates for Measure 1 have been presented in the draft final performance plan for 2023 and 2024. That increase is justified by the staff costs incurred by skeyes for the remuneration of air traffic controller trainees for en route services. The draft final performance plan indicates that those costs had been mistakenly omitted from the costs of Measure 1 in the previous draft performance plans which were submitted for RP3.