36 COMMISSION ASSESSMENT › Assessment of the revised performance targets › Assessment of the capacity-related measures invoked by Luxembourg to justify the observed deviations from the Union-wide cost-efficiency trends › Assessment of modified Measure 1, Decision_act (EU) 2024/343

In forcesince 13 Dec 2023

The Commission already concluded, in Implementing Decision (EU) 2023/1336, that Measure 1 is necessary for the achievement of the local capacity performance targets. However, the Commission considered that Belgium, which is responsible for the supervision of skeyes and for its cost base, had failed to justify, in the revised draft performance plan, the entirety of the costs claimed to be incurred in relation to Measure 1. A portion of the costs of Measure 1 were therefore found to be unjustified in light of the achievement of capacity targets, given that Belgium had not substantiated those costs during the detailed examination referred to recital 1, including with regard to the claimed cost impact of inflation.