33 3. ASSESSMENT › 3.2. Competition assessment › 3.2.3. Market analysis › 3.2.3.2. Renewable electricity generation and wholesale installations that can receive a remuneration independent of market prices (i.e. subject to a fixed feed-in tariff [Section 21 subsection 1 number 1 of the EEG.] and to the tenant electricity surcharge [Section 21 subsection 3 of the EEG.]), Decision_act (EU) 2023/1978

In forcesince 21 Sep 2023

Renewable electricity generation facilities commissioned between 1 January 2012 and 1 August 2014 are exempt from the direct marketing obligation and can use the fixed feed-in tariff option. According to the BkartA, these installations receive a fixed remuneration from a non-market player (the transmission grid operators) and are not involved in any market activity. In line with the analysis performed by the Commission in its 2012 Decision concerning electricity generation and wholesale in Germany, such plants cannot be regarded as being exposed to competition.