20 3. ASSESSMENT › 3.2. Competition assessment › 3.2.1. Relevant product market definition, Decision_act (EU) 2023/1978

In forcesince 21 Sep 2023

In later decisions, the Commission found that conventional and (at least some) renewable electricity generation were part of the same market. In its decision concerning the Netherlands [Commission Implementing Decision (EU) 2018/71 of 12 December 2017 exempting the production and wholesale of electricity in the Netherlands from the application of Directive 2014/25/EU of the European Parliament and of the Council on procurement by entities operating in the water, energy, transport and postal services sector and repealing Directive 2004/17/EC (OJ L 12, 17.1.2018, p. 53).], the Commission noted that the electricity generated from renewable sources was sold directly on the market, and that the Dutch SDE+ system encouraged competitive bids, whereas the competitors would try to minimise their cost (hence the feed in premium they would receive). In its decision concerning Italy [Commission Implementing Decision (EU) 2020/1499 of 28 July 2020 on the applicability of Directive 2014/25/EU of the European Parliament and of the Council to production and wholesale of electricity from renewable sources in Italy (OJ L 342, 16.10.2020, p. 8).], the Commission remarked that the more recent renewable electricity schemes were subject to a bidding process with a high number of applicants. In its decision related to Lithuania [Commission Implementing Decision (EU) 2020/1500 of 28 July 2020 on the applicability of Directive 2014/25/EU of the European Parliament and of the Council to contracts awarded for activities related to production and wholesale of electricity in Lithuania (OJ L 342, 16.10.2020, p. 15).], the Commission stated that electricity produced under the third support scheme received premium-based support established through a competitive bidding procedure and found that it was part of the same market as conventional electricity generation. In 2022 concerning Denmark [Commission Implementing Decision (EU) 2022/1376 of 26 July 2022 on the applicability of Article 34 of Directive 2014/25/EU of the European Parliament and of the Council to electricity generation and wholesale in Denmark (OJ L 206, 8.8.2022, p. 42).], the Commission found that the allocation of the public funding was exposed to competition through a bidding process, which disciplines the behaviour of renewable electricity producers with regard to their procurement policy. As a result, it concluded that the renewable electricity generation facilities subject to the request belonged to the same market as conventional electricity generation.