Art. 16 Directive (EU) 2018/2001

Organisation and main principles of the permit-granting procedure

In forcesince 20 Nov 2023cited 7×
1.

The permit-granting procedure shall cover all relevant administrative permits to build, repower and operate renewable energy plants, including those combining different renewable energy sources, heat pumps, and co-located energy storage, including power and thermal facilities, as well as assets necessary for the connection of such plants, heat pumps and storage to the grid, and to integrate renewable energy into heating and cooling networks, including grid-connection permits and, where required, environmental assessments. The permit-granting procedure shall comprise all administrative stages from the acknowledgment of the completeness of the permit application in accordance with paragraph 2 to the notification of the final decision on the outcome of the permit-granting procedure by the relevant competent authority or authorities.

2.

Within 30 days, for renewable energy plants located in renewables acceleration areas, and within 45 days, for renewable energy plants located outside renewables acceleration areas, of receipt of an application for a permit, the competent authority shall acknowledge the completeness of the application or, if the applicant has not sent all the information required to process the application, request that the applicant submit a complete application without undue delay. The date of acknowledgement of the completeness of the application by the competent authority shall serve as the start of the permit-granting procedure.

3.

Member States shall set up or designate one or more contact points. Those contact points shall, upon the request of the applicant, guide and facilitate the applicant during the entire administrative permit-application and permit-granting procedure. The applicant shall not be required to contact more than one contact point during the entire procedure. The contact point shall guide the applicant through the administrative permit-application procedure, including the steps relating to the protection of the environment, in a transparent manner up to the delivery of one or more decisions by the competent authorities at the end of the permit-granting procedure, provide the applicant with all necessary information and, where appropriate, involve, other administrative authorities. The contact point shall ensure that the deadlines for the permit-granting procedures set out in this Directive are met. Applicants shall be allowed to submit relevant documents in digital form. By 21 November 2025 Member States shall ensure that all permit-granting procedures are carried out in electronic form.

4.

The contact point shall make available a manual of procedures for developers of renewable energy plants and shall provide that information online, addressing distinctly also small-scale renewable energy projects, renewables self-consumers projects and renewable energy communities. The online information shall indicate the contact point relevant to the application in question. If a Member State has more than one contact point, the online information shall indicate the contact point relevant to the application in question.

5.

Member States shall ensure that applicants and the general public have easy access to simple procedures for the settlement of disputes concerning the permit-granting procedure and the issuance of permits to build and operate renewable energy plants, including, where applicable, alternative dispute resolution mechanisms.

6.

Member States shall ensure that administrative and judicial appeals in the context of a project for the development of a renewable energy plant, the connection of that plant to the grid, and the assets necessary for the development of the energy infrastructure networks required to integrate energy from renewable sources into the energy system, including appeals related to environmental aspects, are subject to the most expeditious administrative and judicial procedure that is available at the relevant national, regional and local level.

7.

Member States shall provide adequate resources to ensure qualified staff, upskilling and reskilling of their competent authorities in line with the planned installed renewable energy generation capacity provided for in their integrated national energy and climate plans submitted pursuant to Articles 3 and 14 of Regulation (EU) 2018/1999. Member States shall assist regional and local authorities in order to facilitate the permit-granting procedure.

8.

Except when it coincides with other administrative stages of the permit-granting procedure, the duration of the permit-granting procedure shall not include:

(a)

the time during which the renewable energy plants, their grid connections and, with a view to ensuring grid stability, grid reliability and grid safety, the related necessary grid infrastructure, are being built or repowered;

(b)

the time for the administrative stages necessary for significant upgrades of the grid required to ensuring grid stability, grid reliability and grid safety;

(c)

the time for any judicial appeals and remedies, other proceedings before a court or tribunal, and alternative dispute resolution mechanisms, including complaint procedures and non-judicial appeals and remedies.

9.

Decisions resulting from the permit-granting procedures shall be made publicly available in accordance with the applicable law.

  • Regulation (EU) 2018/199920Law

    … 6 odst. 4 směrnice (EU) 2018/2001; 5) konkrétních opatření ke splnění požadavků článků 15, 16, 17 a 18 směrnice (EU) 2018/2001; 6) případně specifických opatření s cílem posoudit, zprůhlednit a omezit potřebu povinné …

  • Directive (EU) 2023/2413Lawamends

  • Gesetz zur Entwicklung und Förderung der Windenergie auf See66Law

    … für Seeschifffahrt und Hydrographie ist für Zulassungsverfahren nach diesem Gesetz zugleich Anlaufstelle nach Artikel 16 Absatz 3 der Richtlinie (EU) 2018/2001 in der Fassung vom 18. Oktober 2023. (3) Für das Planfeststellungsverfahren …

  • Directive (EU) 2024/17881324Law

    … и звената за контакт, създадени или определени съгласно член 16, параграф 3 от Директива (ЕС) 2018/2001; г) при планирането и …

  • Arrêt de la Cour (huitième chambre) du 22 janvier 2026. Commission européenne contre République de Bulgarie.Decision

    Aux termes de l’article 36, paragraphe 1, de la directive 2018/2001, les États membres devaient mettre en vigueur les dispositions législatives, réglementaires et administratives nécessaires pour se conformer à ses articles 2 à 13, …

    22 Jan 2026 · 62023CJ0206

  • Decision_act (EU) 2025/1430Law

    … на процедурите за издаване на разрешенията, посочени в член 16 от Директива (ЕС) 2018/2001, в решението на Съвместния комитет следва да …

  • Gesetz zur Entwicklung und Förderung der Windenergie auf See66Law