Art. 17 Directive (EU) 2018/2001

Simple-notification procedure for grid connections

In forcecited 4×
1.

Member States shall establish a simple-notification procedure for grid connections whereby installations or aggregated production units of renewables self-consumers and demonstration projects, with an electrical capacity of 10,8 kW or less, or equivalent for connections other than three-phase connections, are to be connected to the grid following a notification to the distribution system operator.

The distribution system operator may, within a limited period following the notification, reject the requested grid connection or propose an alternative grid connection point on justified grounds of safety concerns or technical incompatibility of the system components. In the case of a positive decision by the distribution system operator, or in the absence of a decision by the distribution system operator within one month following the notification, the installation or aggregated production unit may be connected.

2.

Member States may allow a simple-notification procedure for installations or aggregated production units with an electrical capacity of above 10,8 kW and up to 50 kW, provided that grid stability, grid reliability and grid safety are maintained.

  • Regulation (EU) 2018/199920Law

    … 6 odst. 4 směrnice (EU) 2018/2001; 5) konkrétních opatření ke splnění požadavků článků 15, 16, 17 a 18 směrnice (EU) 2018/2001; 6) případně specifických opatření s cílem posoudit, zprůhlednit a omezit potřebu povinné …

  • Directive (EU) 2024/17888Law

    … Pokud povolení ve smyslu odstavce 1 tohoto článku spadá do oblasti působnosti článků 15 a 15b až 17 směrnice (EU) 2018/2001, použijí se pouze uvedená ustanovení.

  • Judgment of the Court (Third Chamber) of 29 July 2024. BP France SAS v Ministre de l’Économie, des Finances et de la Souveraineté industrielDecision

    In that regard, it should be noted that the provisions of Directive 2009/28 and those of Directive 2018/2001 which the Court is required to interpret in the context of this case have an essentially similar object and content for the …

    29 Jul 2024 · 62022CJ0624

  • Arrêt de la Cour (huitième chambre) du 22 janvier 2026. Commission européenne contre République de Bulgarie.Decision

    Dans ses observations déposées le 11 décembre 2024 et le 28 mai 2025, la Commission a reconnu que la République de Bulgarie avait adopté les mesures nécessaires afin d’assurer la conformité de son droit national avec la plupart …

    22 Jan 2026 · 62023CJ0206