Art. 4 Regulation (EU) 2017/2195

Terms and conditions or methodologies of TSOs

In forcesince 15 Mar 2021cited 7×
1.

TSOs shall develop the terms and conditions or methodologies required by this Regulation and submit them for approval to the Agency in accordance with Article 5(2), or to the relevant regulatory authorities in accordance with Article 5(3) within the respective deadlines set out in this Regulation. In exceptional circumstances, notably in cases where a deadline cannot be met due to circumstances external to the sphere of TSOs, the deadlines for terms and conditions or methodologies may be prolonged by the Agency in procedures pursuant to Article 5(2), jointly by all relevant regulatory authorities in procedures pursuant to Article 5(3), and by the relevant regulatory authority in procedures pursuant to Article 5(4).

2.

Where a proposal for terms and conditions or methodologies pursuant to this Regulation needs to be developed and agreed by more than one TSO, the participating TSOs shall closely cooperate. TSOs, with the assistance of the ENTSO for Electricity, shall regularly inform the relevant regulatory authorities and the Agency about the progress of developing those terms and conditions or methodologies.

3.

Where TSOs deciding on proposals for terms and conditions or methodologies listed in Article 5(2) are not able to reach an agreement, they shall decide by qualified majority voting. A qualified majority for proposals listed in Article 5(2) shall require the following majority:

(a)

TSOs representing at least 55 % of the Member States; and

(b)

TSOs representing Member States comprising at least 65 % of the population of the Union.

A blocking minority for decisions on proposals for terms and conditions or methodologies listed in Article 5(2) shall include TSOs representing at least four Member States, failing of which the qualified majority shall be deemed attained.

4.

Where TSOs deciding on proposals for terms and conditions or methodologies listed in Article 5(3) are not able to reach an agreement, and where the regions concerned are composed of more than five Member States, they shall decide by qualified majority voting. A qualified majority for proposals in accordance with Article 5(3) shall require the following majority:

(a)

TSOs representing at least 72 % of the Member States concerned; and

(b)

TSOs representing Member States comprising at least 65 % of the population of the concerned area.

A blocking minority for decisions on proposals for terms and conditions or methodologies listed in Article 5(3) shall include at least a minimum number of TSOs representing more than 35 % of the population of the participating Member States, plus TSOs representing at least one additional Member State concerned, failing of which the qualified majority shall be deemed attained.

5.

TSOs deciding on proposals for terms and conditions or methodologies listed in Article 5(3) in relation to regions composed of five Member States or less shall decide by consensus.

6.

For TSO decisions on proposals for terms and conditions or methodologies pursuant to paragraphs 3 and 4, one vote shall be attributed per Member State. If there is more than one TSO in the territory of a Member State, the Member State shall allocate the voting powers among the TSOs.

7.

Where TSOs fail to submit an initial or amended proposal for terms and conditions or methodologies to the relevant regulatory authorities or the Agency in accordance with Articles 5 and 6 within the deadlines set out in this Regulation, they shall provide the relevant regulatory authorities and the Agency with the relevant drafts of the proposals for terms and conditions or methodologies and explain why an agreement has not been reached. The Agency, all relevant regulatory authorities jointly, or the relevant regulatory authority shall take the appropriate steps for the adoption of the required terms and conditions or methodologies in accordance with Article 5, for instance by requesting amendments or revising and completing the drafts pursuant to this paragraph, including where no drafts have been submitted, and approve them.

  • Gesetz über die Elektrizitäts- und Gasversorgung5659Law

    … Februar 2021, 3. Artikel 5 Absatz 8 der Verordnung (EU) 2017/1485 in der Fassung vom 22. Februar 2021, 4. Artikel 4 Absatz 6 der Verordnung (EU) 2017/2195 in der Fassung vom 25. Mai 2022 und 5. Artikel 15 Absatz 2 der Verordnung (EU) …

  • Regulation (EU) 2021/2803Lawamends

    Články 4 až 7 nařízení (EU) 2017/2195 se nahrazují tímto: 1. Provozovatelé přenosových soustav vypracují podmínky nebo metodiky vyžadované tímto nařízením a předloží je v odpovídajících lhůtách stanovených v …

  • Judgment of the General Court (Third Chamber, Extended Composition) of 25 June 2025. RWE Supply & Trading GmbH v European Union Agency for tDecision

    … ОПС, при условие че получат одобрението от НРО или ACER, въведено с член 4, параграф 1 от Регламент 2017/2195. Всъщност това решение …

    25 Jun 2025 · 62023TJ0095

  • Conseil d'État, 9ème chambre, 26/11/2024, 470863, Inédit au recueil LebonDecision

    26 Nov 2024 · CETATEXT000050667446

  • Conseil d'État, 9ème chambre jugeant seule, 26 novembre 2024, n° 470863, inédit au recueil LebonDecision

    … délibération n° 2022-226 du 28 juillet 2022, la Commission de régulation de l'énergie (CRE), en application des articles 4 à 6 du règlement (UE) 2017/2195 de la Commission européenne du 23 novembre 2017 concernant une ligne …

    26 Nov 2024 · DCE_470863_20241126

  • Conseil d'État, 9ème - 10ème chambres réunies, 17/10/2022, 461073Decision

    17 Oct 2022 · CETATEXT000046441445

  • Conseil d'État, 9ème et 10ème chambres réunies, 17 octobre 2022, n° 461073, mentionné aux tables du recueil LebonDecision

    En premier lieu, aux termes de l'article 4 du règlement du règlement (UE) 2017/2195 de la Commission du 27 novembre 2017 concernant une ligne directrice sur l'équilibrage du système électrique : " 1. Les GRT [gestionnaires du réseau …

    17 Oct 2022 · DCE_461073_20221017