Art. 6 Regulation (EU) 2017/2195

Amendments to terms and conditions or methodologies of TSOs

In forcesince 15 Mar 2021cited 8×
1.

Where the Agency, all relevant regulatory authorities jointly or the relevant regulatory authority require an amendment in order to approve the terms and conditions or methodologies submitted in accordance with Article 5(2), (3) and (4) respectively, the relevant TSOs shall submit a proposal for amended terms and conditions or methodologies for approval within 2 months following the request from the Agency or the relevant regulatory authorities. The Agency or the relevant regulatory authorities shall decide on the amended terms and conditions or methodologies within 2 months following their submission.

2.

Where the relevant regulatory authorities have not been able to reach an agreement on terms and conditions or methodologies within the 2-month deadline, or upon their joint request, or upon the Agency’s request according to the third subparagraph of Article 5(3) of Regulation (EU) 2019/942, the Agency shall adopt a decision concerning the amended terms and conditions or methodologies within 6 months, in accordance with Article 5(3) and the second subparagraph of Article 6(10) of Regulation (EU) 2019/942. If the relevant TSOs fail to submit a proposal for amended terms and conditions or methodologies, the procedure provided for in Article 4 shall apply.

3.

The Agency or the regulatory authorities where they are responsible for the adoption of terms and conditions or methodologies in accordance with Article 5(2), (3) and (4) may respectively request proposals for amendments of those terms and conditions or methodologies and determine a deadline for the submission of those proposals. TSOs responsible for developing a proposal for terms and conditions or methodologies may propose amendments to regulatory authorities and the Agency. The proposals for amendments to the terms and conditions or methodologies shall be submitted to consultation in accordance with the procedure set out in Article 10 and approved in accordance with the procedure set out in Articles 4 and 5.

  • Regulation (EU) 2021/280Lawamends

  • Judgment of the General Court (Second Chamber, Extended Composition) of 15 February 2023. Austrian Power Grid AG and Others v European UnionDecision

    … него в обжалваното решение, апелативният съвет постановява, че член 6, параграф 3 от Регламент 2017/2195 не се прилага за създаването, а …

    15 Feb 2023 · 62020TJ0606

  • Judgment of the General Court (Second Chamber, Extended Composition) of 15 February 2023. Austrian Power Grid AG and Others v European UnionDecision

    … него в обжалваното решение, апелативният съвет постановява, че член 6, параграф 3 от Регламент 2017/2195 не се прилага за създаването, а …

    15 Feb 2023 · 62020TJ0607

  • Conseil d'État, 9ème chambre, 26/11/2024, 470863, Inédit au recueil LebonDecision

    26 Nov 2024 · CETATEXT000050667446

  • Conseil d'État, 9ème chambre jugeant seule, 26 novembre 2024, n° 470863, inédit au recueil LebonDecision

    … délibération n° 2022-226 du 28 juillet 2022, la Commission de régulation de l'énergie (CRE), en application des articles 4 à 6 du règlement (UE) 2017/2195 de la Commission européenne du 23 novembre 2017 concernant une ligne …

    26 Nov 2024 · DCE_470863_20241126

  • Conseil d'État, 9ème - 10ème chambres réunies, 17/10/2022, 461073Decision

    17 Oct 2022 · CETATEXT000046441445

  • EnWGKostVLaw

    … V. m. Artikel 5 Absatz 2 Buchstabe a bis j, Absatz 3 Buchstabe a bis o und Absatz 4 Buchstabe a bis i und Artikel 6 Absatz 3 Satz 2 der Verordnung (EU) 2017/2195 der Kommission vom 23. November 2017 zur Festlegung einer Leitlinie über den …

  • EnWGKostVLaw