Art. 74 Regulation (EU) 2015/1222

Redispatching and countertrading cost sharing methodology

In forcesince 24 Jul 2015cited 10×
1.

No later than 16 months after the decision on the capacity calculation regions is taken, all TSOs in each capacity calculation region shall develop a proposal for a common methodology for redispatching and countertrading cost sharing.

2.

The redispatching and countertrading cost sharing methodology shall include cost-sharing solutions for actions of cross-border relevance.

3.

Redispatching and countertrading costs eligible for cost sharing between relevant TSOs shall be determined in a transparent and auditable manner.

4.

The redispatching and countertrading cost sharing methodology shall at least:

(a)

determine which costs incurred from using remedial actions, for which costs have been considered in the capacity calculation and where a common framework on the use of such actions has been established, are eligible for sharing between all the TSOs of a capacity calculation region in accordance with the capacity calculation methodology set out in Articles 20 and 21;

(b)

define which costs incurred from using redispatching or countertrading to guarantee the firmness of cross-zonal capacity are eligible for sharing between all the TSOs of a capacity calculation region in accordance with the capacity calculation methodology set out in Articles 20 and 21;

(c)

set rules for region-wide cost sharing as determined in accordance with points (a) and (b).

5.

The methodology developed in accordance with paragraph 1 shall include:

(a)

a mechanism to verify the actual need for redispatching or countertrading between the TSOs involved;

(b)

an ex post mechanism to monitor the use of remedial actions with costs;

(c)

a mechanism to assess the impact of the remedial actions, based on operational security and economic criteria;

(d)

a process allowing improvement of the remedial actions;

(e)

a process allowing monitoring of each capacity calculation region by the competent regulatory authorities.

6.

The methodology developed in accordance with paragraph 1 shall also:

(a)

provide incentives to manage congestion, including remedial actions and incentives to invest effectively;

(b)

be consistent with the responsibilities and liabilities of the TSOs involved;

(c)

ensure a fair distribution of costs and benefits between the TSOs involved;

(d)

be consistent with other related mechanisms, including at least:

(i)

the methodology for sharing congestion income set out in Article 73;

(ii)

the inter-TSO compensation mechanism, as set out in Article 13 of Regulation (EC) No 714/2009 and Commission Regulation (EU) No 838/2010 [Commission Regulation (EU) No 838/2010 of 23 September 2010 on laying down guidelines relating to the inter-transmission system operator compensation mechanism and common regulatory approach to transmission charging (OJ L 250, 24.9.2010, p. 5).];

(e)

facilitate the efficient long-term development and operation of the pan-European interconnected system and the efficient operation of the pan-European electricity market;

(f)

facilitate adherence to the general principles of congestion management as set out in Article 16 of Regulation (EC) No 714/2009;

(g)

allow reasonable financial planning;

(h)

be compatible across the day-ahead and intraday market time-frames; and

(i)

comply with the principles of transparency and non-discrimination.

7.

By 31 December 2018, all TSOs of each capacity calculation region shall further harmonise as far as possible between the regions the redispatching and countertrading cost sharing methodologies applied within their respective capacity calculation region.

  • Regulation (EU) 2017/148576Law

    … когато е необходимо, методиките, разработени в съответствие с членове 35 и 74 от Регламент (ЕС) 2015/1222. Предложението определя: а) …

  • Judgment of the General Court (Third Chamber, Extended Composition) of 25 September 2024. Bundesnetzagentur für Elektrizität, Gas, TelekommuDecision

    Accordingly, the contested decision also cannot be deemed to be contrary to Article 74 of Regulation 2015/1222, interpreted in accordance with Article 16(13) of Regulation 2019/943. The Board of Appeal was therefore correct in dismissing …

    25 Sep 2024 · 62021TJ0485

  • Judgment of the General Court (Third Chamber, Extended Composition) of 25 September 2024. Polskie sieci elektroenergetyczne S.A. v European Decision

    The contested cost sharing methodology must, in accordance with Article 74(6)(a) of Regulation 2015/1222, provide incentives to invest effectively to manage congestion. In addition, according to recital 34 of Regulation 2019/943, the …

    25 Sep 2024 · 62021TJ0484

  • Verordnung über die Anreizregulierung der EnergieversorgungsnetzeLaw

    … zu tragenden Anteile im Rahmen der Capacity Allocation & Congestion Management-Methode nach Artikel 74 der Verordnung (EU) 2015/1222 der Kommission vom 24. Juli 2015 zur Festlegung einer Leitlinie für die Kapazitätsvergabe und das …

  • Judgment of the General Court (Third Chamber, Extended Composition) of 25 September 2024. RTE Réseau de transport d'électricité v European UDecision

    It should also be noted that, in the Core region, all remedial actions activated in accordance with the ROSC methodology, as established by Decision No 33/2020, contribute to guaranteeing the firmness of cross-zonal capacity, in accordance …

    25 Sep 2024 · 62021TJ0472

  • Judgment of the General Court (Third Chamber, Extended Composition) of 25 September 2024. Commission de régulation de l’énergie (CRE) v EuroDecision

    It should also be noted that, in the Core region, all remedial actions activated in accordance with the ROSC methodology, as established by Decision No 33/2020, contribute to guaranteeing the firmness of cross-zonal capacity, in accordance …

    25 Sep 2024 · 62021TJ0446

  • Judgment of the General Court (Third Chamber, Extended Composition) of 25 September 2024. Polskie sieci elektroenergetyczne S.A. v European Decision

    In that regard, it should be noted that it is precisely the costs arising as a result of the application of the regional solution that will be shared between the TSOs on the basis of their contribution to congestion, in accordance with the …

    25 Sep 2024 · 62021TJ0483

  • Judgment of the General Court (Third Chamber, Extended Composition) of 25 September 2024. TransnetBW GmbH v European Union Agency for the CoDecision

    It should also be noted that, in the Core region, all remedial actions activated in accordance with the ROSC methodology, as established by Decision No 33/2020, contribute to guaranteeing the firmness of cross-zonal capacity, in accordance …

    25 Sep 2024 · 62021TJ0476

  • Judgment of the General Court (Third Chamber, Extended Composition) of 25 September 2024. TenneT TSO GmbH and TenneT TSO BV v European UnionDecision

    It should also be noted that, in the Core region, all remedial actions activated in accordance with the ROSC methodology, as established by Decision No 33/2020, contribute to guaranteeing the firmness of cross-zonal capacity, in accordance …

    25 Sep 2024 · 62021TJ0482

  • Verordnung über die Anreizregulierung der EnergieversorgungsnetzeLaw