Art. 28 Regulation (EU) 2015/1222

Creation of a common grid model

In forcesince 24 Jul 2015cited 3×
1.

For each capacity calculation time-frame referred to in Article 14(1), each generator or load unit subject to Article 16 shall provide the data specified in the generation and load data provision methodology to the TSO responsible for the respective control area within the specified deadlines.

2.

Each generator or load unit providing information pursuant to Article 16(3) shall deliver the most reliable set of estimations practicable.

3.

For each capacity calculation time-frame, each TSO shall establish the individual grid model for each scenario in accordance with Article 19, in order to merge individual grid models into a common grid model.

4.

Each TSO shall deliver to the TSOs responsible for merging the individual grid models into a common grid model the most reliable set of estimations practicable for each individual grid model.

5.

For each capacity calculation time-frame a single, Union-wide common grid model shall be created for each scenario as set out in Article 18 by merging inputs from all TSOs applying the capacity calculation process as set out in paragraph 3 of this Article.

  • Regulation (EU) 2016/171922Law

    Процедурата и изискванията, определени в член 28 от Регламент (ЕС) 2015/1222 за създаване на модел на обща електроенергийна мрежа, се …

  • Regulation (EU) 2017/148579Law

    … в член 67, параграф 1 и член 70, параграф 1, и в съответствие с член 28 от Регламент (ЕС) 2015/1222 координаторът за регионалната сигурност се …

  • Systeemcode elektriciteitLaw

    … coordinators: ”In accordance with the methodologies referred to in Articles 67(1) and 70(1), and in accordance with Article 28 of Regulation (EU) 2015/1222, a regional security coordinator shall be appointed by all TSOs to build the …