2011 | 2012 | 2013 | | 2014-2017
1st Q | 2nd Q | 3rd Q | 4th Q | | | |
ACTIVITIES | SECONDARY ACTIVITIES | PREPARATORY PHASE | | | | OPERATIONAL PHASE
AWARENESS RAISING AND GENERAL INFORMATION
1- Produce and evaluate a communications plan
2- Implement the communications plan
3- Develop and update the Internet site
INSTITUTIONAL FRAMEWORK
1- Transpose/officially recognise the responsibilities (as described in this Agreement) of the different verification and verification control structures and update the MEFCP’s organic text
2- Establish and run the joint consultation mechanism
3- Establish the Joint Implementation and Monitoring Committee
4- Establish and run the National Agreement Implementation and Monitoring Committee
5- Establish a Permanent Technical Secretariat (STP)
CAPACITY BUILDING
1- Train the actors in relation to elements of the Voluntary Partnership Agreement) (VPA)
2- Produce a training and capacity building plan for the different verification and verification control structures, along with civil society and the private sector
3- Implement the training plan
4- Establish equipment and logistical needs
5- Acquire equipment and logistical tools
6- Make offices available (STP, ICEF, BMIV, CDF, licensing authority)
7- Establish the Customs Conciliation and Expertise Commission (CCED) and train staff
REFORM OF THE LEGAL FRAMEWORK
1- Develop regulations according to the legality definition in Annex II
2- Improve the legal framework relating to the domestic timber market
3- Improve the legal framework relating to forests (community, communal and private forests) and plantations
4- Procedure for ratifying the VPA
5- Produce a non-compliance management manual
6- Develop legal measures to improve governance (organic text, monitoring, national tracking system, etc.)
ESTABLISHING THE NATIONAL TRACKING SYSTEM (NTS)
1- Finalise procedures relating to the NTS (methods, controls, verifications, etc.), including TEREA mission.
2- Implement the planned national tracking system (NTS)
3- Establish links between the databases of the main structures involved
4- Design then establish database links with CEMAC countries
5- Acquire materials and equipment (identifiers, identifier readers, computers)
6- Roll out the system at national level: establish and equip checkpoints along the supply chains, including border posts (infrastructure, computers, Internet links, etc.)
7- Strengthen the capacity of the actors (MEFCP and other departments involved, private sector and civil society)
8- Train staff involved (ICEF, CDF, BMIV and other ministries), private sector and civil society
ESTABLISHING THE SCHEME FOR LEGALITY ASSURANCE (LAS)
1- Where appropriate, produce legality matrices relating to artisanal permits and community forests, to include field tests
2- Each body responsible for verification (public administration) to develop/strengthen its verification procedures, in cooperation with ICEF
3- Develop information exchange protocols on legality assurance between the public administration and ICEF.
4- Develop operational procedures for running the SGBD
5- Pilot test FLEGT licensing scheme and put required actions in place
6- Company preparation test in the procedures for verifying and issuing FLEGT licences
7- Training (particularly for BMIV members) and awareness raising on the procedures for verifying the legality of the logging entity
8- Operational evaluation of the LAS, in accordance with Article 12 of the Agreement
9- LAS up and running
SYSTEM FOR ISSUING LICENCES
1- Establish the licensing authority
2- Raise awareness of the detailed procedures for issuing FLEGT licences within the private sector
3- Establish contacts with the competent Union authorities
4- Issue FLEGT licences
INDEPENDENT SYSTEM AUDITS
1- Recruit the independent auditor and develop a detailed methodology (from March 2013)
2- First audit, then successive audits
PRODUCT PROMOTION STRATEGY
1- Produce a promotional plan, including a study of the current markets
2- Position and promote FLEGT products coming from the CAR on the targeted markets
MONITORING THE IMPACTS OF THE VPA
1- Define and monitor social indicators
2- Establish a system for monitoring confiscated timber
3- Establish a system for monitoring socio-economic and environmental impacts
4- Assess the socio-economic impact midway through VPA implementation
5- Monitor and assess forest sector revenues
SEEKING ADDITIONAL FINANCING
1- Develop a fundraising strategy