Recital 18, Decision_act (EU) 2001/597

In force

Production Costs at Blaentillery No 2 should be around GBP [...]GJ in 2002; these costs are [...] % higher than those calculated for the reference period. Certain financial difficulties have not allowed this production unit to make the investments necessary to replace some of its production capacities in time. The resulting drop in production has meant an increase in production cost per unit of coal extracted. Given their current state of development, the new capacities should be going into production during 2002. There should therefore be a very significant reduction in production costs in subsequent years. According to the United Kingdom authorities, costs should fall by [...] % between 2002 and 2004 and by about [...] % between the reference period and 2004. The production costs should therefore be below the GBP 1,15/GJ threshold referred to in recital 15 as from 2003, with a cost level of about GBP [...]GJ.