Accordingly, the Italian authorities decided to reorganise the airport system of Milan in order to create a hub at Malpensa and provide adequate airport capacity for the future. That objective is to be achieved through the extension and upgrading of Malpensa airport, known as the Malpensa 2000 project. This project is one of the 14 priority projects of the trans-European network under Decision No 1692/96/EC of the European Parliament and of the Council (2). It is financially supported by the Community, the European Investment Fund and the European Investment Bank (EIB). Construction works for a new terminal started in 1990. A first section will be operating in 1998 with a yearly capacity of 12 million passengers (which will add to existing capacity of 6 million) and the terminal will be fully completed in 2000. The overall capacity of the airport (existing and new terminal) will, by then, reach 24 million passengers.