Cartonboard production is a highly automated and capital intensive process. In order to be viable, a large new cartonboard mill would need to have a capacity of 150 000 to 200 000 tonnes and would cost around ECU 250 million to build. This was in fact the case of the new M-M/FS-Karton mill which came on stream in Germany at about the end of 1990.
The cartonboard producers consider that the ideal method of operation is to run their machines at full capacity 24 hours a day and 350 to 355 days per year. To operate economically, large machines require long production runs with the minimum of product changes. Each production run is tailored to suit the requirements of the individual customer or of several customers grouped together. Virtually all the cartonboard manufactured in western Europe is produced for specific orders; it is not generally practicable to manufacture for stock. The number of days or weeks of orders in hand (order backlog) is thus a good indicator of the strength of demand. In the event that the order backlog falls below two to three weeks, the larger producers will generally consider it advisable to halt production temporarily ('take downtime') in order to improve the production programme and ensure the maintenance of product quality. Smaller mills have somewhat more flexibility.