ANNEX IV, Decision_act (EU) 1994/421

In forcesince 16 Dec 1993

MONITORING AND ASSESSMENT 1. The national body responsible for implementation shall be fully involved in the monitoring and assessment of projects. In order to carry out these obligations, the Member States may request a Community contribution from the Commission as technical support.

A. Monitoring

2.

Monitoring means a system of information on the progress made in implementing the project. Monitoring shall use financial and, where appropriate, physical indicators which enable actual progress on completion of the project to be compared with the financing plan in Annex II and the schedule for implementation in Annex I.

3.

The implementation of projects shall be monitored by means of:

–

the Monitoring Committee set up by each Member State concerned,

–

reports,

–

sample checks.

Monitoring Committee

4.

The Monitoring Committee set up to monitor projects financed by the cohesion financial instrument in Spain shall be responsible for monitoring the project which is the subject of this Decision. The Committee shall review its implementation at regular intervals and, where necessary, propose any adjustments required.

The composition of the Monitoring Committee, including appointment of its chairman, its operation and frequency of meetings, shall be adopted by joint agreement between the Member State and the Commission, not later than three months after the approval of the first project in Spain.

5.

The Committee shall:

(a)

monitor the proper implementation of the project and ensure that it achieves the objectives laid down for it in accordance with the plan originally adopted;

(b)

give its opinion on the draft annual reports on implementation referred to in point 6;

(c)

propose, when appropriate, the necessary measure to ensure that the project achieves the objectives laid down for it;

(d)

ensure publicity for the project;

(e)

ensure that Community policies are respected, especially environment policy;

(f)

decide by agreement between the Commission and the Member State any additional responsibilities of the Committee.

In general, the documents required for meetings of the Committee shall be available three weeks in advance.

Reports

6.

In accordance with Article 25 (4) of Regulation (EEC) No 4253/88, annual reports for each complete year of implementation and a final report shall be drawn up for the project which is the subject of this Decision.

The first annual report on this project shall be submitted to the Commission by the authority responsible no later than 15 months after adoption of the Decision approving the project. The report shall contain the following information:

–

progress of the project,

–

details of any divergence from the implementation plan originally laid down,

–

an outline of the main problems encountered and the measures taken to solve them.

On the basis of the information in the annual reports, the Commission and the Member State may, where necessary, revise the financing plan for the project and make adjustments to it.

The final report, to be submitted six months after physical completion of the project, shall report on the work carried out and its conformity with the Decision approving the project and give an initial appraisal of the chances of achieving the results sought.

Payment of the balance of Community assistance shall be subject to approval of the final report.

Checks

7.

Checks may be carried out in accordance with Article 23 (2) of Regulation (EEC) No 4253/88 by both the Member State and the Commission. The Member State and the Commission shall immediately exchange any relevant information concerning the results.

8.

For a period of three years following the last payment in respect of the project, the authority responsible for implementation shall keep available for the Commission all the supporting documents regarding expenditure.

9.

The Member State shall keep available for the Commission all appropriate national reports concerning the checks carried out.

B. Assessment

10.

An assessment of the project may be carried out during its implementation at the request of the Member State or on the initiative of the Commission in order to assess whether the project is progressing in accordance with the objectives originally laid down and to propose adjustments to take account of problems encountered during implementation. The Monitoring Committee shall take into account this evaluation.

11.

An ex-post assessment of the impact of the project may be carried out by an assessor appointed by joint agreement between the Member State and the Commission once the project has been completed.