, Decision_act (EU) 1993/564

In forcesince 22 Jul 1993

The provincial authorities would, however, prefer that the expansion take place not in Riva del Garda but rather in Mori, 20 km away. Riva del Garda is popular with tourists and additional industrial activities there would not improve this town's touristic attraction but rather impair its environmental situation.

If Cartiere del Garda should decide to install its new machine in Mori, whilst its present plant in Riva remained as it is for the rest of its useful life, this choice would entail additional investment and operating cost when compared with an expansion in Riva. The additional investments are caused by the differences between a greenfield site (Mori) and a brownfield site (Riva), the additional operating cost being due to additional personnel and transport between the two sites if Mori is chosen.

The PAT intends to compensate the additional investment cost at Mori if Cartiere del Garda should choose that site, but would not compensate the additional operating cost. The legal basis for this compensation would be Article 1 of Provincial law No 7/91.

II By letter dated 11 December 1992, registered on 15 December, the Commission was informed of the intention of the PAT to apply Article 1 of Provincial law No 7/91 in favour of Cartiere del Garda's expansion project in Mori. Additional information was provided by letter dated 20 January 1993. Information had previously been submitted on the law and on this first project by the provincial authorities by letter dated 15 June 1992, in a bilateral meeting held on 2 July 1992 and by letter dated 12 November 1992. The beneficiary company and the group to which it belongs had submitted information in a bilateral meeting held on 9 November and by letter dated 9 December 1992.