Art. 2a Directive (EU) 1992/13

Standstill period

In forcesince 17 Apr 2014cited 7×
1.

The Member States shall ensure that the persons referred to in Article 1(3) have sufficient time for effective review of the contract award decisions taken by contracting entities, by adopting the necessary provisions respecting the minimum conditions set out in paragraph 2 of this Article and in Article 2c.

2.

A contract may not be concluded following the decision to award a contract falling within the scope of Directive 2014/25/EU or Directive 2014/23/EU before the expiry of a period of at least 10 calendar days with effect from the day following the date on which the contract award decision is sent to the tenderers and candidates concerned if fax or electronic means are used or, if other means of communication are used, before the expiry of a period of either at least 15 calendar days with effect from the day following the date on which the contract award decision is sent to the tenderers and candidates concerned or at least 10 calendar days with effect from the day following the date of the receipt of the contract award decision.

Tenderers shall be deemed to be concerned if they have not yet been definitively excluded. An exclusion is definitive if it has been notified to the tenderers concerned and has either been considered lawful by an independent review body or can no longer be subject to a review procedure.

Candidates shall be deemed to be concerned if the contracting entity has not made available information about the rejection of their application before the notification of the contract award decision to the tenderers concerned.

The communication of the award decision to each tenderer and candidate concerned shall be accompanied by the following:

a summary of the relevant reasons as set out in Article 75(2) of Directive 2014/25/EU, subject to the provisions of Article 75(3) of that Directive or in the second subparagraph of Article 40(1) of Directive 2014/23/EU, subject to the provisions of Article 40(2) of that Directive, and

a precise statement of the exact standstill period applicable pursuant to the provisions of national law transposing this paragraph.

  • Judgment of the Court (Eighth Chamber) of 11 May 2017. Archus sp. z o.o. and Gama Jacek Lipik v Polskie Górnictwo Naftowe i Gazownictwo S.A.Decision

    The third paragraph of Article 2a(2) of Directive 92/13 provides as follows: ‘Candidates shall be deemed to be concerned if the contracting entity has not made available information about the rejection of their application before the …

    11 May 2017 · 62016CJ0131

  • Judgment of the Court (Tenth Chamber) of 24 March 2021. NAMA Symvouloi Michanikoi kai Meletites A.E. – LDK Symvouloi Michanikoi A.E. and OthDecisioninterprets

    This request for a preliminary ruling concerns the interpretation of Article 1(3), Article 2(1)(a) and (b), and Article 2a(2) of Council Directive 92/13/EEC of 25 February 1992 coordinating the laws, regulations and administrative …

    24 Mar 2021 · 62019CJ0771

  • Judgment of the Court (Second Chamber) of 10 November 2011. Norma-A SIA and Dekom SIA v Latgales plānošanas reģions.Decision

    According to Article 2d(1)(b) of Directive 92/13, Member States are to ensure that a contract is considered ineffective by a review body independent of the contracting entity or that its ineffectiveness is the result of a decision of such …

    10 Nov 2011 · 62010CJ0348

  • Judgment of the Court (Fifth Chamber), 8 May 2014. Idrodinamica Spurgo Velox srl and Others v Acquedotto Pugliese SpA.Decisioninterprets

    This request for a preliminary ruling concerns the interpretation of Articles 1, 2a, 2c and 2f of Council Directive 92/13/EEC of 25 February 1992 coordinating the laws, regulations and administrative provisions relating to the application …

    8 May 2014 · 62013CJ0161

  • Opinion of Mr Advocate General Cruz Villalón delivered on 7 July 2011. Norma-A SIA and Dekom SIA v Latgales plānošanas reģions.Decision

    If these provisions of Directive 89/665 have been held to be ‘unconditional and sufficiently clear’, those contained in Article 2d(1)(b) of Directive 92/13 can be no less so, subject to the exception which I will go on to mention, …

    7 Jul 2011 · 62010CC0348

  • Judgment of the Court (Ninth Chamber) of 24 February 2022. Alstom Transport SA v Compania Naţională de Căi Ferate CFR SA and Others.Decision

    Under Article 2a(2) of Directive 92/13: ‘… The communication of the award decision to each tenderer and candidate concerned shall be accompanied by the following: a summary of the relevant reasons as set out in Article 75(2) of …

    24 Feb 2022 · 62020CJ0532

  • Opinion of Advocate General Bobek delivered on 21 November 2019. HUNGEOD Közlekedésfejlesztési, Földmérési, Út- és Vasúttervezési Kft. and ODecision

    That reading is further confirmed by the context and purpose of Article 1(3) of the Remedies Directives, as amended by Directive 2007/66. First, as regards the overall context of Article 1(3), the EU legislature has introduced mechanisms …

    21 Nov 2019 · 62018CC0496