Art. 1 Directive (EU) 1992/13

Scope and availability of review procedures

In forcesince 17 Apr 2014cited 44×
1.

This Directive applies to contracts referred to in Directive 2014/25/EU of the European Parliament and of the Council [Directive 2014/25/EU of the European Parliament and of the Council of 26 February 2014 on procurement by entities operating in the water, energy, transport and postal services sectors (OJ L 94, 28.3.2014, p. 243).] unless such contracts are excluded in accordance with Articles 18 to 24, 27 to 30, 34 or 55 of that Directive.

Contracts within the meaning of this Directive include supply, works and service contracts, works and services concessions, framework agreements and dynamic purchasing systems.

This Directive also applies to concessions awarded by contracting entities, referred to in Directive 2014/23/EU of the European Parliament and of the Council [Directive 2014/23/EU of the European Parliament and of the Council of 26 February 2014 on the award of concessions contract (OJ L 94, 28.3.2014, p. 1).] unless such contracts are excluded in accordance with Articles 10, 12, 13, 14, 16, 17 and 25 of that Directive.

Member States shall take the measures necessary to ensure that, as regards contracts falling within the scope of Directive 2014/25/EU or Directive 2014/23/EU, decisions taken by contracting entities may be reviewed effectively and, in particular, as rapidly as possible in accordance with the conditions set out in Articles 2 to 2f of this Directive, on the grounds that such decisions have infringed Union law in the field of procurement or national rules transposing that law.

2.

Member States shall ensure that there is no discrimination between undertakings likely to make a claim in respect of harm in the context of a procedure for the award of a contract as a result of the distinction made by this Directive between national rules implementing Community law and other national rules.

3.

Member States shall ensure that the review procedures are available, under detailed rules which the Member States may establish, at least to any person having or having had an interest in obtaining a particular contract and who has been or risks being harmed by an alleged infringement.

4.

Member States may require that the person wishing to use a review procedure has notified the contracting entity of the alleged infringement and of his intention to seek review, provided that this does not affect the standstill period in accordance with Article 2a(2) or any other time limits for applying for review in accordance with Article 2c.

5.

Member States may require that the person concerned first seek review with the contracting entity. In that case, Member States shall ensure that the submission of such an application for review results in immediate suspension of the possibility to conclude the contract.

Member States shall decide on the appropriate means of communication, including fax or electronic means, to be used for the application for review provided for in the first subparagraph.

The suspension referred to in the first subparagraph shall not end before the expiry of a period of at least 10 calendar days with effect from the day following the date on which the contracting entity has sent a reply if fax or electronic means are used, or, if other means of communication are used, before the expiry of a period of either at least 15 calendar days with effect from the day following the date on which the contracting entity has sent a reply or at least 10 calendar days with effect from the day following the date of the receipt of a reply.

The 10 that are cited most themselves, of 44.

  • Directive (EU) 2007/66Lawamends

  • Directive (EU) 2014/23Lawamends

  • Judgment of the Court (Tenth Chamber) of 24 March 2021. NAMA Symvouloi Michanikoi kai Meletites A.E. – LDK Symvouloi Michanikoi A.E. and OthDecisioninterprets

    This request for a preliminary ruling concerns the interpretation of Article 1(3), Article 2(1)(a) and (b), and Article 2a(2) of Council Directive 92/13/EEC of 25 February 1992 coordinating the laws, regulations and administrative …

    24 Mar 2021 · 62019CJ0771

  • Judgment of the Court (Third Chamber) of 15 September 2016. SC Star Storage SA and Others v Institutul Naţional de Cercetare-Dezvoltare în IDecisioninterprets

    These requests for a preliminary ruling concern the interpretation of Article 1(1) to (3) of Council Directive 89/665/EEC of 21 December 1989 on the coordination of the laws, regulations and administrative provisions relating to the …

    15 Sep 2016 · 62014CJ0439

  • Judgment of the Court (Fourth Chamber) of 17 June 2021. Simonsen & Weel A/S v Region Nordjylland og Region Syddanmark.Decision

    Article 1 of Directive 92/13, which is entitled ‘Scope and availability of review procedures’, provides, in the first and second subparagraphs of paragraph 1 thereof: ‘This Directive applies to the contracts referred to in Directive …

    17 Jun 2021 · 62020CJ0023

  • Judgment of the Court (Second Chamber) of 3 March 2005. Fabricom SA v Belgian State.Decisioninterprets

    The references for a preliminary ruling concern the interpretation of Council Directive 92/50/EEC of 18 June 1992 relating to the coordination of procedures for the award of public service contracts (OJ 1992 L 209, p. 1), as amended by …

    3 Mar 2005 · 62003CJ0021

  • Judgment of the Court (Tenth Chamber) of 23 November 2023. EVN Business Service GmbH and Others.Decision

    In those circumstances the Verwaltungsgerichtshof (Supreme Administrative Court) decided to stay the proceedings and to refer the following questions to the Court of Justice for a preliminary ruling: Must Article 57(3) of [Directive …

    23 Nov 2023 · 62022CJ0480

  • Judgment of the Court (Fourth Chamber) of 29 July 2019. Hochtief Solutions AG Magyarországi Fióktelepe v Fővárosi Törvényszék.Decision

    In those circumstances, the Székesfehérvári Törvényszék (Székesfehérvár High Court) decided to stay the proceedings and to refer the following questions to the Court for a preliminary ruling: Are the basic principles and rules of …

    29 Jul 2019 · 62017CJ0620

  • Judgment of the Court (Eighth Chamber) of 11 May 2017. Archus sp. z o.o. and Gama Jacek Lipik v Polskie Górnictwo Naftowe i Gazownictwo S.A.Decisioninterprets

    … of the tender of the successful tenderer, so that the concept of ‘a particular contract’ within the meaning of Article 1(3) of Directive 92/13, as amended by Directive 2007/66, may, where appropriate, apply to the possible initiation …

    11 May 2017 · 62016CJ0131

  • Judgment of the Court (Second Chamber) of 10 November 2011. Norma-A SIA and Dekom SIA v Latgales plānošanas reģions.Decision

    By its questions, which it is appropriate to examine together, the national court is asking whether, if the contract at issue in the main proceedings is regarded as a ‘public service contract’ within the meaning of Directive 2004/17, …

    10 Nov 2011 · 62010CJ0348