Art. 2 Directive (EU) 1992/13

Requirements for review procedures

In forcesince 9 Jan 2008cited 37×
1.

The Member States shall ensure that the measures taken concerning the review procedures specified in Article 1 include provision for the powers:

either

(a)

to take, at the earliest opportunity and by way of interlocutory procedure, interim measures with the aim of correcting the alleged infringement or preventing further injury to the interests concerned, including measures to suspend or to ensure the suspension of the procedure for the award of a contract or the implementation of any decision taken by the contracting entity; and

(b)

to set aside or ensure the setting aside of decisions taken unlawfully, including the removal of discriminatory technical, economic or financial specifications in the notice of contract, the periodic indicative notice, the notice on the existence of a system of qualification, the invitation to tender, the contract documents or in any other document relating to the contract award procedure in question;

or

(c)

to take, at the earliest opportunity, if possible by way of interlocutory procedures and if necessary by a final procedure on the substance, measures other than those provided for in points (a) and (b) with the aim of correcting any identified infringement and preventing injury to the interests concerned; in particular, making an order for the payment of a particular sum, in cases where the infringement has not been corrected or prevented.

Member States may take this choice either for all contracting entities or for categories of entities defined on the basis of objective criteria, in any event preserving the effectiveness of the measures laid down in order to prevent injury being caused to the interests concerned;

(d)

and, in both the above cases, to award damages to persons injured by the infringement.

Where damages are claimed on the grounds that a decision has been taken unlawfully, Member States may, where their system of internal law so requires and provides bodies having the necessary powers for that purpose, provide that the contested decision must first be set aside or declared illegal.

2.

The powers specified in paragraph 1 and Articles 2d and 2e may be conferred on separate bodies responsible for different aspects of the review procedure.

3.

When a body of first instance, which is independent of the contracting entity, reviews a contract award decision, Member States shall ensure that the contracting entity cannot conclude the contract before the review body has made a decision on the application either for interim measures or for review. The suspension shall end no earlier than the expiry of the standstill period referred to in Article 2a(2) and Article 2d(4) and (5).

3a.

Except where provided for in paragraph 3 and Article 1(5), review procedures need not necessarily have an automatic suspensive effect on the contract award procedures to which they relate.

4.

Member States may provide that the body responsible for review procedures may take into account the probable consequences of interim measures for all interests likely to be harmed, as well as the public interest, and may decide not to grant such measures when their negative consequences could exceed their benefits.

A decision not to grant interim measures shall not prejudice any other claim of the person seeking such measures.

5.

The sum to be paid in accordance with paragraph 1 (c) must be set at a level high enough to dissuade the contracting entity from committing or persisting in an infringement. The payment of that sum may be made to depend upon a final decision that the infringenemt has in fact taken place.

6.

Except where provided for in Articles 2d to 2f, the effects of the exercise of the powers referred to in paragraph 1 of this Article on a contract concluded subsequent to its award shall be determined by national law.

Furthermore, except where a decision must be set aside prior to the award of damages, a Member State may provide that, after the conclusion of a contract in accordance with Article 1(5), paragraph 3 of this Article or Articles 2a to 2f, the powers of the body responsible for review procedures shall be limited to awarding damages to any person harmed by an infringement.

7.

Where a claim is made for damages representing the costs of preparing a bid or of participating in an award procedure, the person making the claim shall be required only to prove an infringement of Community law in the field of procurement or national rules implementing that law and that he would have had a real chance of winning the contract and that, as a consequence of that infringement, that chance was adversely affected.

8.

The Member States shall ensure that decisions taken by bodies responsible for review procedures can be effectively enforced.

9.

Whereas bodies responsible for review procedures are not judicial in character, written reasons for their decisions shall always be given. Furthermore, in such a case, provision must be made to guarantee procedures whereby any allegedly illegal measures taken by the review body or any alleged defect in the exercise of the powers conferred on it can be the subject of judicial review or review by another body which is a court or tribunal within the meaning of Article 234 of the Treaty and independent of both the contracting entity and the review body.

The members of the independent body referred to in the first paragraph shall be appointed and leave office under the same conditions as members of the judiciary as regards the authority responsible for their appointment, their period of office, and their removal. At least the President of this independent body shall have the same legal and professional qualifications as members of the judiciary. The independent body shall take its decisions following a procedure in which both sides are heard, and these decisions shall, by means determined by each Member State, be legally binding.

The 10 that are cited most themselves, of 37.

  • Directive (EU) 2007/66Lawamends

  • Judgment of the Court (Second Chamber) of 3 March 2005. Fabricom SA v Belgian State.Decisioninterprets

    The references for a preliminary ruling concern the interpretation of Council Directive 92/50/EEC of 18 June 1992 relating to the coordination of procedures for the award of public service contracts (OJ 1992 L 209, p. 1), as amended by …

    3 Mar 2005 · 62003CJ0021

  • Judgment of the Court (Fourth Chamber) of 29 July 2019. Hochtief Solutions AG Magyarországi Fióktelepe v Fővárosi Törvényszék.Decision

    In those circumstances, the Székesfehérvári Törvényszék (Székesfehérvár High Court) decided to stay the proceedings and to refer the following questions to the Court for a preliminary ruling: Are the basic principles and rules of …

    29 Jul 2019 · 62017CJ0620

  • Judgment of the Court (Eighth Chamber) of 11 May 2017. Archus sp. z o.o. and Gama Jacek Lipik v Polskie Górnictwo Naftowe i Gazownictwo S.A.Decision

    Denne fortolkning bekræftes af bestemmelserne i artikel 2a, stk. 1, og 2, i direktiv 92/13, som udtrykkeligt foreskriver, at tilbudsgivere, der ikke er blevet endeligt udelukket, skal have en ret til bl.a. at klage over ordregiveres …

    11 May 2017 · 62016CJ0131

  • Judgment of the Court (Tenth Chamber) of 24 March 2021. NAMA Symvouloi Michanikoi kai Meletites A.E. – LDK Symvouloi Michanikoi A.E. and OthDecision

    This request for a preliminary ruling concerns the interpretation of Article 1(3), Article 2(1)(a) and (b), and Article 2a(2) of Council Directive 92/13/EEC of 25 February 1992 coordinating the laws, regulations and administrative …

    24 Mar 2021 · 62019CJ0771

  • Judgment of the Court (Third Chamber) of 7 August 2018. Hochtief AG v Budapest Főváros Önkormányzata.Decision

    That action having been dismissed at first instance and on appeal, Hochtief brought an appeal in cassation before the referring court, claiming, inter alia, an infringement of Article 2(1) of Directive 89/665 and Article 2(1) of Council …

    7 Aug 2018 · 62017CJ0300

  • Judgment of the Court (Second Chamber) of 10 November 2011. Norma-A SIA and Dekom SIA v Latgales plānošanas reģions.Decision

    According to Article 2d(1)(b) of Directive 92/13, Member States are to ensure that a contract is considered ineffective by a review body independent of the contracting entity or that its ineffectiveness is the result of a decision of such …

    10 Nov 2011 · 62010CJ0348

  • Judgment of the Court (Third Chamber) of 11 June 2009. Commission of the European Communities v French Republic.Decision

    11 Jun 2009 · 62008CJ0327

  • Judgment of the Court (Sixth Chamber) of 24 September 1998. EvoBus Austria GmbH v Niederösterreichische Verkehrsorganisations GmbH (Növog).Decisioninterprets

    By the first and second questions, which it is appropriate to deal with together, the national court is essentially asking whether Articles 1(1) to (3) and 2(1) and (7) to (9) or any other provisions of Directive 92/13 must be interpreted …

    24 Sep 1998 · 61997CJ0111

  • Judgment of the Court (Sixth Chamber) of 19 May 1999. Commission of the European Communities v French Republic.Decision

    The first point to note is that it is common ground that the Commission does not dispute the French Republic's decision to avail itself of the option provided for in Article 2(1 )(c) of the Directive.

    19 May 1999 · 61997CJ0225