Art. 2c Directive (EU) 1989/665

Time limits for applying for review

In forcesince 17 Apr 2014cited 12×

Where a Member State provides that any application for review of a contracting authority's decision taken in the context of, or in relation to, a contract award procedure falling within the scope of Directive 2014/24/EU or Directive 2014/23/EU must be made before the expiry of a specified period, this period shall be at least 10 calendar days with effect from the day following the date on which the contracting authority's decision is sent to the tenderer or candidate if fax or electronic means are used or, if other means of communication are used, this period shall be either at least 15 calendar days with effect from the day following the date on which the contracting authority's decision is sent to the tenderer or candidate or at least 10 calendar days with effect from the day following the date of the receipt of the contracting authority's decision. The communication of the contracting authority's decision to each tenderer or candidate shall be accompanied by a summary of the relevant reasons. In the case of an application for review concerning decisions referred to in Article 2(1)(b) of this Directive that are not subject to a specific notification, the time period shall be at least 10 calendar days from the date of the publication of the decision concerned.

The 10 that are cited most themselves, of 12.

  • Judgment of the Court (Third Chamber) of 28 January 2010. Uniplex (UK) Ltd v NHS Business Services Authority.Decision

    The same conclusion is also supported by the amendments made to Directive 89/665 by Directive 2007/66/EC of the European Parliament and of the Council of 11 December 2007 amending Council Directives 89/665/EEC and 92/13/EEC with regard to …

    28 Jan 2010 · 62008CJ0406

  • Judgment of the Court (Grand Chamber) of 7 September 2021. 'Klaipėdos regiono atliekų tvarkymo centras' v UAB.Decision

    In that regard, it follows from the fourth subparagraph of Article 1(1) of Directive 89/665 that the Member States are to take the measures necessary to ensure that, as regards inter alia contracts falling within the scope of Directive …

    7 Sep 2021 · 62019CJ0927

  • Order of the Court (Fourth Chamber) of 14 February 2019. Cooperativa Animazione Valdocco S.C.S. Impresa Sociale Onlus v Consorzio IntercomunDecisioninterprets

    … amended by Directive 2014/23/EU of the European Parliament and of the Council of 26 February 2014, and in particular Articles 1 and 2c thereof, read in the light of Article 47 of the Charter of Fundamental Rights of the European Union, …

    14 Feb 2019 · 62018CO0054

  • Opinion of Advocate General Kokott delivered on 13 March 2008. pressetext Nachrichtenagentur GmbH v Republik Österreich (Bund), APA-OTS OrigDecision

    … raisonnable [Voir également sur ce point l’article 2 septies, paragraphe 1, sous b), lu en combinaison avec l’article 2 quater, paragraphe 1, de la directive 89/665, telle que modifiée par la directive 2007/66.]. En effet, les …

    13 Mar 2008 · 62006CC0454

  • Opinion of Advocate General Kokott delivered on 29 October 2009. Uniplex (UK) Ltd v NHS Business Services Authority.Decision

    Directive 89/665 makes no express provision on the time-limits that apply to review procedures under Article 1 of the directive. (12) However, the Court has consistently held that the Member States may in the exercise of their procedural …

    29 Oct 2009 · 62008CC0406

  • Judgment of the Court (Fifth Chamber) of 26 November 2015. MedEval - Qualitäts-, Leistungs- und Struktur-Evaluierung im Gesundheitswesen GmbDecision

    As regards all the other legal actions concerning public contracts, including actions for damages, Article 2f(2) of Directive 89/665 states that, subject to the provisions of Article 2c of that directive, not relevant to the question …

    26 Nov 2015 · 62014CJ0166

  • Opinion of Advocate General Campos Sánchez-Bordona delivered on 7 September 2023. CROSS Zlín, a.s. v Úřad pro ochranu hospodářské soutěže.Decision

    Accordingly, a court may, if national legislation so provides (which does not appear to be the case in the Czech Republic), act as a body of first instance under Article 2(3) of Directive 89/665.

    7 Sep 2023 · 62022CC0303

  • Opinion of Advocate General Kokott delivered on 29 October 2009. European Commission v Ireland.Decision

    Directive 89/665 makes no express provision on the time-limits that apply to review procedures under Article 1 of the directive. (21) However, the Court has consistently held that the Member States may in the exercise of their procedural …

    29 Oct 2009 · 62008CC0456

  • VwGH 12.09.2013, 2010/04/0066Decision

    … Auch unionsrechtlich ist nicht anderes geboten, weil Art. 2c der Richtlinie 89/665/EWG, zuletzt geändert durch die Richtlinie 2007/66/EG, für die Stellung eines Nachprüfungsantrages gegen Entscheidungen eines öffentlichen Auftraggebers …

    12 Sep 2013 · JWT_2010040066_20130912X00

  • Judgment of the Court (Eighth Chamber) of 14 July 2022. EPIC Financial Consulting Ges.m.b.H. v Republik Österreich and Bundesbeschaffung GmbDecision

    In that regard, it should be borne in mind that, under the fourth subparagraph of Article 1(1) of Directive 89/665, the Member States must take the measures necessary to ensure that, as regards public contracts falling inter alia within …

    14 Jul 2022 · 62021CJ0274