Art. 2 Directive (EU) 1989/665

Requirements for review procedures

In forcesince 9 Jan 2008cited 217×
1.

Member States shall ensure that the measures taken concerning the review procedures specified in Article 1 include provision for powers to:

(a)

take, at the earliest opportunity and by way of interlocutory procedures, interim measures with the aim of correcting the alleged infringement or preventing further damage to the interests concerned, including measures to suspend or to ensure the suspension of the procedure for the award of a public contract or the implementation of any decision taken by the contracting authority;

(b)

either set aside or ensure the setting aside of decisions taken unlawfully, including the removal of discriminatory technical, economic or financial specifications in the invitation to tender, the contract documents or in any other document relating to the contract award procedure;

(c)

award damages to persons harmed by an infringement.

2.

The powers specified in paragraph 1 and Articles 2d and 2e may be conferred on separate bodies responsible for different aspects of the review procedure.

3.

When a body of first instance, which is independent of the contracting authority, reviews a contract award decision, Member States shall ensure that the contracting authority cannot conclude the contract before the review body has made a decision on the application either for interim measures or for review. The suspension shall end no earlier than the expiry of the standstill period referred to in Article 2a(2) and Article 2d(4) and (5).

4.

Except where provided for in paragraph 3 and Article 1(5), review procedures need not necessarily have an automatic suspensive effect on the contract award procedures to which they relate.

5.

Member States may provide that the body responsible for review procedures may take into account the probable consequences of interim measures for all interests likely to be harmed, as well as the public interest, and may decide not to grant such measures when their negative consequences could exceed their benefits.

A decision not to grant interim measures shall not prejudice any other claim of the person seeking such measures.

6.

Member States may provide that where damages are claimed on the grounds that a decision was taken unlawfully, the contested decision must first be set aside by a body having the necessary powers.

7.

Except where provided for in Articles 2d to 2f, the effects of the exercise of the powers referred to in paragraph 1 of this Article on a contract concluded subsequent to its award shall be determined by national law.

Furthermore, except where a decision must be set aside prior to the award of damages, a Member State may provide that, after the conclusion of a contract in accordance with Article 1(5), paragraph 3 of this Article or Articles 2a to 2f, the powers of the body responsible for review procedures shall be limited to awarding damages to any person harmed by an infringement.

8.

Member States shall ensure that decisions taken by bodies responsible for review procedures can be effectively enforced.

9.

Where bodies responsible for review procedures are not judicial in character, written reasons for their decisions shall always be given. Furthermore, in such a case, provision must be made to guarantee procedures whereby any allegedly illegal measure taken by the review body or any alleged defect in the exercise of the powers conferred on it can be the subject of judicial review or review by another body which is a court or tribunal within the meaning of Article 234 of the Treaty and independent of both the contracting authority and the review body.

The members of such an independent body shall be appointed and leave office under the same conditions as members of the judiciary as regards the authority responsible for their appointment, their period of office, and their removal. At least the President of this independent body shall have the same legal and professional qualifications as members of the judiciary. The independent body shall take its decisions following a procedure in which both sides are heard, and these decisions shall, by means determined by each Member State, be legally binding.

The 10 that are cited most themselves, of 217.

  • Directive (EU) 2007/66Lawamends

  • Judgment of the Court (Sixth Chamber) of 28 October 1999. Alcatel Austria AG and Others, Siemens AG Österreich and Sag-Schrack AnlagentechniDecisioninterprets

    In those circumstances, the Bundesvergabeamt decided to stay proceedings and refer the following questions to the Court for a preliminary ruling: When implementing Directive 89/665/EEC, are Member States required by Article 2(6) thereof to …

    28 Oct 1999 · 61998CJ0081

  • Judgment of the Court (Sixth Chamber) of 18 June 2002. Hospital Ingenieure Krankenhaustechnik Planungs-Gesellschaft mbH (HI) v Stadt Wien.Decisioninterprets

    By order of 17 February 2000, received at the Court on 10 March 2000, the Vergabekontrollsenat des Landes Wien (Public-Procurement Review Chamber of the Vienna Region) referred to the Court for a preliminary ruling under Article 234 EC …

    18 Jun 2002 · 62000CJ0092

  • Judgment of the Court of 17 September 1997. Dorsch Consult Ingenieurgesellschaft mbH v Bundesbaugesellschaft Berlin mbH.Decision

    Το άρθρο 2, παράγραφος 8, της οδηγίας 89/665 προβλέπει τα ακόλουθα: «Όταν οι υπεύθυνες για τις διαδικασίες προσφυγής αρχές δεν είναι …

    17 Sep 1997 · 61996CJ0054

  • Judgment of the Court (Sixth Chamber) of 12 February 2004. Grossmann Air Service, Bedarfsluftfahrtunternehmen GmbH & Co. KG v Republik ÖsterDecisioninterprets

    By decision of 4 January 1999, the Bundesvergabeamt dismissed Grossmann's application pursuant to Paragraphs 115(1) and 113(2) and (3) of the BVergG, on the ground that Grossmann had failed to assert its legal interest in obtaining the …

    12 Feb 2004 · 62002CJ0230

  • Judgment of the Court (Sixth Chamber) of 19 June 2003. Gesellschaft für Abfallentsorgungs-Technik GmbH (GAT) v Österreichische Autobahnen unDecision

    As the Bundesvergabeamt considered that an interpretation of several provisions of Community law was required in order to enable it to give a decision in the case before it, it decided to stay proceedings and refer the following questions …

    19 Jun 2003 · 62001CJ0315

  • Judgment of the Court (Sixth Chamber) of 27 February 2003. Santex SpA v Unità Socio Sanitaria Locale n. 42 di Pavia, and Sca Mölnlycke SpA, Decision

    Under Article 2(1)(b) of Directive 89/665: ‘The Member States shall ensure that the measures taken concerning the review procedures specified in Article 1 include provision for the powers to: ... either set aside or ensure the setting …

    27 Feb 2003 · 62000CJ0327

  • Judgment of the Court (Sixth Chamber) of 4 February 1999. Josef Köllensperger GmbH & Co. KG and Atzwanger AG v Gemeindeverband BezirkskrankeDecisioninterprets

    By order of 7 November 1996, received at the Court on 10 March 1997, the Tiroler Landesvergabeamt (Procurement Office of the Land of Tyrol) referred to the Court for a preliminary ruling under Article 1 77 of the EC Treaty two questions on …

    4 Feb 1999 · 61997CJ0103

  • Judgment of the Court (First Chamber) of 11 January 2005. Stadt Halle and RPL Recyclingpark Lochau GmbH v Arbeitsgemeinschaft Thermische ResDecision

    The wording of Article 1(1) of Directive 89/665 assumes, by using the words ‘as regards ... procedures’, that every decision of a contracting authority falling under the Community rules in the field of public procurement and liable to …

    11 Jan 2005 · 62003CJ0026

  • Judgment of the Court (Fifth Chamber), 11 September 2014. Ministero dell’Interno v Fastweb SpA.Decision

    The third subparagraph of Article 1(1) of Directive 89/665 requires Member States to take measures to ensure that decisions taken by the contracting authorities may be reviewed effectively and, in particular, as rapidly as possible in …

    11 Sep 2014 · 62013CJ0019