Where the client is a domestic client the duties in regulations 4(1) to (7) and 6 shall be carried out by—
the contractor for a project where there is only one contractor;
the principal contractor for a project where there is more than one contractor; or
the principal designer where there is written agreement that the principal designer will fulfil those duties.
If a domestic client fails to make appointments required by regulation 5—
the designer in control of the pre-construction phase of the project is the principal designer;
the contractor in control of the construction phase of the project is the principal contractor.
Regulation 5(3) and (4) does not apply to a domestic client.