Commission Implementing Decision of 7 May 2012 concerning the determination of start-up…, 3

General rules for determining start-up and shut-down periods

In forcesince 7 May 2012

For determining the end of the start-up period and the beginning of the shut-down period, the following rules shall apply:

the criteria or parameters used to determine start-up and shut-down periods shall be transparent and externally verifiable;

the determination of start-up and shut-down periods shall be based on conditions allowing a stable generation process safeguarding health and safety;

periods during which a combustion plant, after start-up, is operating stably and safely with fuel supply but without the export of heat or electricity or mechanical energy shall not be included in the start-up or shut-down periods.