RA 2011, s. 38

Construction certificates

In forcesince 12 Apr 2011cited 1×
(1)

The construction engineer must give the reservoir manager a construction certificate as soon as is reasonably practicable after being satisfied that the construction or (as the case may be) alteration has been completed to a satisfactory standard.

(2)

The construction certificate must in any event be issued not later than the final certificate in respect of the works.

(3)

A construction certificate must—

(a)

certify that the construction or (as the case may be) alteration has been executed effectively in accordance with the drawings and descriptions included in the annex to the certificate,

(b)

include an annex containing detailed drawings and descriptions giving full information about the works for the construction or (as the case may be) the alteration, including the dimensions, water levels and details of the geological strata or deposits encountered in trial holes or excavations made in connection with the works,

(c)

include such other information as the Scottish Ministers by regulations require.

(4)

The construction engineer must, not later than 28 days after giving a construction certificate, give SEPA a copy of it.

  • The Reservoirs (Scotland) Regulations 201630Law

    A construction certificate by a construction engineer under section 38 (construction certificates) of the Act must— (a) in addition to the information required by subsection (3)(a) and (b) of that section, contain the other information …