Art. 12 Regulation (EU) 2026/562

Aid for the construction, upgrade and renewal of unimodal and multimodal railway service and inland waterways facilities

In forcesince 16 Mar 2026
1.

Aid for the construction, upgrade and renewal (including the replacement) of railway service facilities, inland waterways facilities and rail or inland waterways multimodal transport facilities shall be compatible with the internal market within the meaning of Article 93 of the Treaty and shall be exempted from the notification requirement of Article 108(3) of the Treaty, provided that the conditions laid down in this Article and in Chapter I are fulfilled.

2.

The aid must be granted to owners or operators of a railway service facility, inland waterways facility or rail or inland waterways multimodal transport facility that construct, upgrade or renew such a facility on the basis of schemes, except for aid for the construction, upgrade and renewal of rail or inland waterways freight terminals, which may also be granted as ad hoc aid. Where ad hoc aid is granted, the ex ante estimated potential demand for capacity, at least in the medium term, must exceed the combined capacity of the aided facility and of other existing or already planned facilities that could reasonably serve as alternatives to the aided facility.

3.

The eligible costs shall be the investment costs in tangible (fixed and movable) and intangible assets directly related to the construction, upgrade or renewal of the relevant facility. The investment costs shall include surface arrangements (such as for storage), fixed equipment (such as warehouses and terminal buildings), equipment used for the operation of the facility (such as reach stackers) located in the facility, and IT and digital equipment and software for the provision of transport-related services. Costs arising from feasibility and topological studies, as well as planning and installation costs, shall also be eligible.

4.

Costs related to non-transport activities shall not be eligible.

5.

The aid amount must not exceed the lower of the following thresholds:

(a)

the difference between, on the one hand, the eligible costs and, on the other hand, the sum of the discounted operating profit of the investment over its economic lifetime and the discounted terminal value of that investment (residual value at the end of the economic lifetime of the investment). The discounted operating profit shall also include the incremental operating net profits generated by non-transport activities connected to the transport activities to be carried out in the facility concerned (such as the rental of commercial spaces situated in the facility). The discounted operating profit and terminal value shall be deducted from the eligible costs ex ante, on the basis of reasonable projections, or ex post through a claw-back mechanism. The aid amount may allow for a reasonable profit to be made. The reasonable profit shall be determined with respect to the typical profit for the sector and type of project concerned. In any event, a rate of return on capital that does not exceed the relevant swap rate plus a premium of 100 basis points shall be considered reasonable;

(b)

50 % of the eligible costs.

6.

By way of derogation from paragraph 5, for aid not exceeding EUR 5 million per project, aid must be granted up to a maximum aid intensity of 50 % of the eligible costs.

7.

The aid intensity may be increased up to 10 percentage points for facilities located along the TEN-T.

8.

Access to the aided facility must be open, transparent and non-discriminatory and must be provided to all interested users in line with sectoral legislation, including Directive 2012/34/EU.

9.

Any concession or other entrustment to a third party to construct, upgrade, operate or rent the aided facility must be assigned on a competitive, transparent, non-discriminatory and unconditional basis.

10.

When the owner, operator and any projected end user of the aided facility are part of the same enterprise or are linked enterprises within the meaning of Annex I, the operation of the facility must be awarded based on an open, competitive, transparent and non-discriminatory procedure, in which the linked enterprises, if any, shall be allowed to participate. This paragraph shall not apply to aid for the upgrade of railway service facilities, inland waterways facilities and rail or inland waterways multimodal transport facilities where the investment costs of the upgrade over a period of at least five years do not exceed 10 % of the value of the initial investment.