Art. 3 Decision_act (EU) 2026/994

In forcesince 4 May 2026

The derogation granted under Article 1 shall apply only for the purposes of the Sustainable Berlenga project.

The Portuguese authorities shall ensure that all following conditions are met:

(a)

the Sustainable Berlenga project is implemented under conditions that aim to increase competition and integration of the internal market and that do not obstruct the transition towards renewable energy, increased flexibility, energy storage, electromobility or demand response;

(b)

the National Regulatory Authority (NRA) is able to observe and monitor the costs of the Sustainable Berlenga project;

(c)

the unbundling of accounts requirement set out in Article 56 of Directive (EU) 2019/944 applies also to the Sustainable Berlenga project, and E-REDES or a new concessionaire keeps separate accounts for the ownership and operation of the generation assets;

(d)

the costs of the Sustainable Berlenga project are not recovered through distribution network tariffs in order to avoid cross-subsidies, but through separate resources.