51 CONCLUSIONS, Decision_act (EU) 2026/865

In forcesince 27 Mar 2026

Finally, the Commission did not find, based on the elements and justifications provided in the revised draft FABEC performance plan, that the deviation from the long-term Union-wide DUC trend could be exclusively attributed to additional costs incurred for capacity measures. Further information and analysis would be required in order to examine other operational and economic considerations raised by the Netherlands to justify the deviations observed in recitals 16, 17 and 20 in respect of the asessment criteria set out in points 1.4 (a), (b) and (c) of Annex IV of Implementing Regulation (EU) 2019/317.