Art. 32 Regulation (EU) 2024/1789

Union-wide network development plan for natural gas

In forcesince 13 Jun 2024cited 2×

The ENTSO for Gas shall adopt and publish the Union-wide network development plan for natural gas every two years. The Union-wide network development plan for natural gas shall include the modelling of the integrated network, scenario development, a European supply adequacy outlook and an assessment of the resilience of the system, including infrastructure to be decommissioned.

The Union-wide network development plan for natural gas shall, in particular:

(a)

build on national investment plans and Chapter IV of Regulation (EU) 2022/869;

(b)

regarding cross-border interconnections, also build on the reasonable needs of different network users and integrate long-term commitments from investors as referred to in Article 55(7) of Directive (EU) 2024/1788; and

(c)

identify investment gaps, in particular with respect to cross-border capacities.

With regard to the second paragraph, point (c), a review of barriers to the increase of cross-border capacity of the network arising from different approval procedures or practices may be annexed to the Union-wide network development plan for natural gas.

  • Directive (EU) 2024/1788555778Law

    … за развитие на мрежата за природен газ в целия Съюз, посочен в член 32 от Регламент (ЕС) 2024/1789, и с десетгодишния план за развитие на …

  • Gesetz über die Elektrizitäts- und Gasversorgung15cLaw

    … In dem Netzentwicklungsplan Gas und Wasserstoff sind der gemeinschaftsweite Netzentwicklungsplan für Erdgas nach Artikel 32 der Verordnung (EU) 2024/1789 sowie der gemeinschaftsweite Netzentwicklungsplan für Wasserstoff nach Artikel 60 …