Bidding zones are designed to avoid grid congestion within the zone. To ensure that there is no electricity grid congestion between the electrolyser producing renewable hydrogen and the installation generating renewable electricity it is appropriate to require that, both installations should be located in the same bidding zone. Where they are located in interconnected bidding zones, the electricity price in the bidding zone where the installation generating renewable electricity is located should be equal or higher than in the bidding zone where the renewable liquid and gaseous transport fuel of non-biological origin is produced so that it contributes to reducing congestion; or the installation generating renewable electricity under the power purchase agreement should be located in an offshore bidding zone interconnected to the bidding zone where the electrolyser is located.
Recital 12, Regulation (EU) 2023/1184
In forcesince 10 Feb 2023